Browse the full platform hierarchy from shared platform modules through assemblies, Parts, and approved SKU alternates. Search and scope filters support product, module, supplier, region, and revision storytelling.
| Backup Generation Assembly 1 Part 1 approved primary SKU | Vertex Modular | $183.9k | 23 weeks | NA · CA | |
| Backup Generation Assembly 1 Part 1 approved alternate SKU | OmniControls | $208.4k | 24 weeks | EMEA · NL |
| Backup Generation Assembly 1 Part 2 approved primary SKU | BlueRiver Fabrication | $189.4k | 25 weeks | APAC · AU | |
| Backup Generation Assembly 1 Part 2 approved alternate SKU | Atlas Switchgear | $213.8k | 8 weeks | NA · US |
| Backup Generation Assembly 1 Part 3 approved primary SKU | Kinetic Thermal | $181.2k | 9 weeks | EMEA · AE | |
| Backup Generation Assembly 1 Part 3 approved alternate SKU | Apex Power Systems | $205.7k | 10 weeks | APAC · AU |
| Backup Generation Assembly 1 Part 4 approved primary SKU | Northstar Electrical | $186.6k | 11 weeks | NA · CA | |
| Backup Generation Assembly 1 Part 4 approved alternate SKU | HelioCool | $211.1k | 12 weeks | EMEA · FR |
| Backup Generation Assembly 1 Part 5 approved primary SKU | Vertex Modular | $192.1k | 13 weeks | APAC · AU | |
| Backup Generation Assembly 1 Part 5 approved alternate SKU | OmniControls | $202.9k | 14 weeks | NA · US |
| Backup Generation Assembly 2 Part 1 approved primary SKU | BlueRiver Fabrication | $183.9k | 15 weeks | EMEA · ES | |
| Backup Generation Assembly 2 Part 1 approved alternate SKU | Atlas Switchgear | $208.4k | 16 weeks | APAC · AU |
| Backup Generation Assembly 2 Part 2 approved primary SKU | Kinetic Thermal | $189.4k | 17 weeks | NA · CA | |
| Backup Generation Assembly 2 Part 2 approved alternate SKU | Apex Power Systems | $213.8k | 18 weeks | EMEA · DE |
| Backup Generation Assembly 2 Part 3 approved primary SKU | Northstar Electrical | $181.2k | 19 weeks | APAC · AU | |
| Backup Generation Assembly 2 Part 3 approved alternate SKU | HelioCool | $205.7k | 20 weeks | NA · US |
| Backup Generation Assembly 2 Part 4 approved primary SKU | Vertex Modular | $186.6k | 21 weeks | EMEA · IE | |
| Backup Generation Assembly 2 Part 4 approved alternate SKU | OmniControls | $211.1k | 22 weeks | APAC · AU |
| Backup Generation Assembly 2 Part 5 approved primary SKU | BlueRiver Fabrication | $192.1k | 23 weeks | NA · CA | |
| Backup Generation Assembly 2 Part 5 approved alternate SKU | Atlas Switchgear | $202.9k | 24 weeks | EMEA · GB |
| Backup Generation Assembly 3 Part 1 approved primary SKU | Kinetic Thermal | $183.9k | 25 weeks | APAC · AU | |
| Backup Generation Assembly 3 Part 1 approved alternate SKU | Apex Power Systems | $208.4k | 8 weeks | NA · US |
| Backup Generation Assembly 3 Part 2 approved primary SKU | Northstar Electrical | $189.4k | 9 weeks | EMEA · NL | |
| Backup Generation Assembly 3 Part 2 approved alternate SKU | HelioCool | $213.8k | 10 weeks | APAC · AU |
| Backup Generation Assembly 3 Part 3 approved primary SKU | Vertex Modular | $181.2k | 11 weeks | NA · CA | |
| Backup Generation Assembly 3 Part 3 approved alternate SKU | OmniControls | $205.7k | 12 weeks | EMEA · AE |
| Backup Generation Assembly 3 Part 4 approved primary SKU | BlueRiver Fabrication | $186.6k | 13 weeks | APAC · AU | |
| Backup Generation Assembly 3 Part 4 approved alternate SKU | Atlas Switchgear | $211.1k | 14 weeks | NA · US |
| Backup Generation Assembly 3 Part 5 approved primary SKU | Kinetic Thermal | $192.1k | 15 weeks | EMEA · FR | |
| Backup Generation Assembly 3 Part 5 approved alternate SKU | Apex Power Systems | $202.9k | 16 weeks | APAC · AU |
| Backup Generation Assembly 4 Part 1 approved primary SKU | Northstar Electrical | $183.9k | 17 weeks | NA · CA | |
| Backup Generation Assembly 4 Part 1 approved alternate SKU | HelioCool | $208.4k | 18 weeks | EMEA · ES |
| Backup Generation Assembly 4 Part 2 approved primary SKU | Vertex Modular | $189.4k | 19 weeks | APAC · AU | |
| Backup Generation Assembly 4 Part 2 approved alternate SKU | OmniControls | $213.8k | 20 weeks | NA · US |
| Backup Generation Assembly 4 Part 3 approved primary SKU | BlueRiver Fabrication | $181.2k | 21 weeks | EMEA · DE | |
| Backup Generation Assembly 4 Part 3 approved alternate SKU | Atlas Switchgear | $205.7k | 22 weeks | APAC · AU |
| Backup Generation Assembly 4 Part 4 approved primary SKU | Kinetic Thermal | $186.6k | 23 weeks | NA · CA | |
| Backup Generation Assembly 4 Part 4 approved alternate SKU | Apex Power Systems | $211.1k | 24 weeks | EMEA · IE |
| Backup Generation Assembly 4 Part 5 approved primary SKU | Northstar Electrical | $192.1k | 25 weeks | APAC · AU | |
| Backup Generation Assembly 4 Part 5 approved alternate SKU | HelioCool | $202.9k | 8 weeks | NA · US |
| Backup Generation Assembly 5 Part 1 approved primary SKU | Vertex Modular | $183.9k | 9 weeks | EMEA · GB | |
| Backup Generation Assembly 5 Part 1 approved alternate SKU | OmniControls | $208.4k | 10 weeks | APAC · AU |
| Backup Generation Assembly 5 Part 2 approved primary SKU | BlueRiver Fabrication | $189.4k | 11 weeks | NA · CA | |
| Backup Generation Assembly 5 Part 2 approved alternate SKU | Atlas Switchgear | $213.8k | 12 weeks | EMEA · NL |
| Backup Generation Assembly 5 Part 3 approved primary SKU | Kinetic Thermal | $181.2k | 13 weeks | APAC · AU | |
| Backup Generation Assembly 5 Part 3 approved alternate SKU | Apex Power Systems | $205.7k | 14 weeks | NA · US |
| Backup Generation Assembly 5 Part 4 approved primary SKU | Northstar Electrical | $186.6k | 15 weeks | EMEA · AE | |
| Backup Generation Assembly 5 Part 4 approved alternate SKU | HelioCool | $211.1k | 16 weeks | APAC · AU |
| Backup Generation Assembly 5 Part 5 approved primary SKU | Vertex Modular | $192.1k | 17 weeks | NA · CA | |
| Backup Generation Assembly 5 Part 5 approved alternate SKU | OmniControls | $202.9k | 18 weeks | EMEA · FR |
| Controls and Telemetry Assembly 1 Part 1 approved primary SKU | BlueRiver Fabrication | $191.2k | 19 weeks | APAC · AU | |
| Controls and Telemetry Assembly 1 Part 1 approved alternate SKU | Atlas Switchgear | $216.7k | 20 weeks | NA · US |
| Controls and Telemetry Assembly 1 Part 2 approved primary SKU | Kinetic Thermal | $196.9k | 21 weeks | EMEA · ES | |
| Controls and Telemetry Assembly 1 Part 2 approved alternate SKU | Apex Power Systems | $222.3k | 22 weeks | APAC · AU |
| Controls and Telemetry Assembly 1 Part 3 approved primary SKU | Northstar Electrical | $188.4k | 23 weeks | NA · CA | |
| Controls and Telemetry Assembly 1 Part 3 approved alternate SKU | HelioCool | $213.8k | 24 weeks | EMEA · DE |
| Controls and Telemetry Assembly 1 Part 4 approved primary SKU | Vertex Modular | $194.1k | 25 weeks | APAC · AU | |
| Controls and Telemetry Assembly 1 Part 4 approved alternate SKU | OmniControls | $219.5k | 8 weeks | NA · US |
| Controls and Telemetry Assembly 1 Part 5 approved primary SKU | BlueRiver Fabrication | $199.7k | 9 weeks | EMEA · IE | |
| Controls and Telemetry Assembly 1 Part 5 approved alternate SKU | Atlas Switchgear | $211k | 10 weeks | APAC · AU |
| Controls and Telemetry Assembly 2 Part 1 approved primary SKU | Kinetic Thermal | $191.2k | 11 weeks | NA · CA | |
| Controls and Telemetry Assembly 2 Part 1 approved alternate SKU | Apex Power Systems | $216.7k | 12 weeks | EMEA · GB |
| Controls and Telemetry Assembly 2 Part 2 approved primary SKU | Northstar Electrical | $196.9k | 13 weeks | APAC · AU | |
| Controls and Telemetry Assembly 2 Part 2 approved alternate SKU | HelioCool | $222.3k | 14 weeks | NA · US |
| Controls and Telemetry Assembly 2 Part 3 approved primary SKU | Vertex Modular | $188.4k | 15 weeks | EMEA · NL | |
| Controls and Telemetry Assembly 2 Part 3 approved alternate SKU | OmniControls | $213.8k | 16 weeks | APAC · AU |
| Controls and Telemetry Assembly 2 Part 4 approved primary SKU | BlueRiver Fabrication | $194.1k | 17 weeks | NA · CA | |
| Controls and Telemetry Assembly 2 Part 4 approved alternate SKU | Atlas Switchgear | $219.5k | 18 weeks | EMEA · AE |
| Controls and Telemetry Assembly 2 Part 5 approved primary SKU | Kinetic Thermal | $199.7k | 19 weeks | APAC · AU | |
| Controls and Telemetry Assembly 2 Part 5 approved alternate SKU | Apex Power Systems | $211k | 20 weeks | NA · US |
| Controls and Telemetry Assembly 3 Part 1 approved primary SKU | Northstar Electrical | $191.2k | 21 weeks | EMEA · FR | |
| Controls and Telemetry Assembly 3 Part 1 approved alternate SKU | HelioCool | $216.7k | 22 weeks | APAC · AU |
| Controls and Telemetry Assembly 3 Part 2 approved primary SKU | Vertex Modular | $196.9k | 23 weeks | NA · CA | |
| Controls and Telemetry Assembly 3 Part 2 approved alternate SKU | OmniControls | $222.3k | 24 weeks | EMEA · ES |
| Controls and Telemetry Assembly 3 Part 3 approved primary SKU | BlueRiver Fabrication | $188.4k | 25 weeks | APAC · AU | |
| Controls and Telemetry Assembly 3 Part 3 approved alternate SKU | Atlas Switchgear | $213.8k | 8 weeks | NA · US |
| Controls and Telemetry Assembly 3 Part 4 approved primary SKU | Kinetic Thermal | $194.1k | 9 weeks | EMEA · DE | |
| Controls and Telemetry Assembly 3 Part 4 approved alternate SKU | Apex Power Systems | $219.5k | 10 weeks | APAC · AU |
| Controls and Telemetry Assembly 3 Part 5 approved primary SKU | Northstar Electrical | $199.7k | 11 weeks | NA · CA | |
| Controls and Telemetry Assembly 3 Part 5 approved alternate SKU | HelioCool | $211k | 12 weeks | EMEA · IE |
| Controls and Telemetry Assembly 4 Part 1 approved primary SKU | Vertex Modular | $191.2k | 13 weeks | APAC · AU | |
| Controls and Telemetry Assembly 4 Part 1 approved alternate SKU | OmniControls | $216.7k | 14 weeks | NA · US |
| Controls and Telemetry Assembly 4 Part 2 approved primary SKU | BlueRiver Fabrication | $196.9k | 15 weeks | EMEA · GB | |
| Controls and Telemetry Assembly 4 Part 2 approved alternate SKU | Atlas Switchgear | $222.3k | 16 weeks | APAC · AU |
| Controls and Telemetry Assembly 4 Part 3 approved primary SKU | Kinetic Thermal | $188.4k | 17 weeks | NA · CA | |
| Controls and Telemetry Assembly 4 Part 3 approved alternate SKU | Apex Power Systems | $213.8k | 18 weeks | EMEA · NL |
| Controls and Telemetry Assembly 4 Part 4 approved primary SKU | Northstar Electrical | $194.1k | 19 weeks | APAC · AU | |
| Controls and Telemetry Assembly 4 Part 4 approved alternate SKU | HelioCool | $219.5k | 20 weeks | NA · US |
| Controls and Telemetry Assembly 4 Part 5 approved primary SKU | Vertex Modular | $199.7k | 21 weeks | EMEA · AE | |
| Controls and Telemetry Assembly 4 Part 5 approved alternate SKU | OmniControls | $211k | 22 weeks | APAC · AU |
| Controls and Telemetry Assembly 5 Part 1 approved primary SKU | BlueRiver Fabrication | $191.2k | 23 weeks | NA · CA | |
| Controls and Telemetry Assembly 5 Part 1 approved alternate SKU | Atlas Switchgear | $216.7k | 24 weeks | EMEA · FR |
| Controls and Telemetry Assembly 5 Part 2 approved primary SKU | Kinetic Thermal | $196.9k | 25 weeks | APAC · AU | |
| Controls and Telemetry Assembly 5 Part 2 approved alternate SKU | Apex Power Systems | $222.3k | 8 weeks | NA · US |
| Controls and Telemetry Assembly 5 Part 3 approved primary SKU | Northstar Electrical | $188.4k | 9 weeks | EMEA · ES | |
| Controls and Telemetry Assembly 5 Part 3 approved alternate SKU | HelioCool | $213.8k | 10 weeks | APAC · AU |
| Controls and Telemetry Assembly 5 Part 4 approved primary SKU | Vertex Modular | $194.1k | 11 weeks | NA · CA | |
| Controls and Telemetry Assembly 5 Part 4 approved alternate SKU | OmniControls | $219.5k | 12 weeks | EMEA · DE |
| Controls and Telemetry Assembly 5 Part 5 approved primary SKU | BlueRiver Fabrication | $199.7k | 13 weeks | APAC · AU | |
| Controls and Telemetry Assembly 5 Part 5 approved alternate SKU | Atlas Switchgear | $211k | 14 weeks | NA · US |
| Facility Support Assembly 1 Part 1 approved primary SKU | Northstar Electrical | $205.8k | 11 weeks | NA · CA | |
| Facility Support Assembly 1 Part 1 approved alternate SKU | HelioCool | $233.2k | 12 weeks | EMEA · AE |
| Facility Support Assembly 1 Part 2 approved primary SKU | Vertex Modular | $211.9k | 13 weeks | APAC · AU | |
| Facility Support Assembly 1 Part 2 approved alternate SKU | OmniControls | $239.3k | 14 weeks | NA · US |
| Facility Support Assembly 1 Part 3 approved primary SKU | BlueRiver Fabrication | $202.8k | 15 weeks | EMEA · FR | |
| Facility Support Assembly 1 Part 3 approved alternate SKU | Atlas Switchgear | $230.2k | 16 weeks | APAC · AU |
| Facility Support Assembly 1 Part 4 approved primary SKU | Kinetic Thermal | $208.9k | 17 weeks | NA · CA | |
| Facility Support Assembly 1 Part 4 approved alternate SKU | Apex Power Systems | $236.3k | 18 weeks | EMEA · ES |
| Facility Support Assembly 1 Part 5 approved primary SKU | Northstar Electrical | $215k | 19 weeks | APAC · AU | |
| Facility Support Assembly 1 Part 5 approved alternate SKU | HelioCool | $227.1k | 20 weeks | NA · US |
| Facility Support Assembly 2 Part 1 approved primary SKU | Vertex Modular | $205.8k | 21 weeks | EMEA · DE | |
| Facility Support Assembly 2 Part 1 approved alternate SKU | OmniControls | $233.2k | 22 weeks | APAC · AU |
| Facility Support Assembly 2 Part 2 approved primary SKU | BlueRiver Fabrication | $211.9k | 23 weeks | NA · CA | |
| Facility Support Assembly 2 Part 2 approved alternate SKU | Atlas Switchgear | $239.3k | 24 weeks | EMEA · IE |
| Facility Support Assembly 2 Part 3 approved primary SKU | Kinetic Thermal | $202.8k | 25 weeks | APAC · AU | |
| Facility Support Assembly 2 Part 3 approved alternate SKU | Apex Power Systems | $230.2k | 8 weeks | NA · US |
| Facility Support Assembly 2 Part 4 approved primary SKU | Northstar Electrical | $208.9k | 9 weeks | EMEA · GB | |
| Facility Support Assembly 2 Part 4 approved alternate SKU | HelioCool | $236.3k | 10 weeks | APAC · AU |
| Facility Support Assembly 2 Part 5 approved primary SKU | Vertex Modular | $215k | 11 weeks | NA · CA | |
| Facility Support Assembly 2 Part 5 approved alternate SKU | OmniControls | $227.1k | 12 weeks | EMEA · NL |
| Facility Support Assembly 3 Part 1 approved primary SKU | BlueRiver Fabrication | $205.8k | 13 weeks | APAC · AU | |
| Facility Support Assembly 3 Part 1 approved alternate SKU | Atlas Switchgear | $233.2k | 14 weeks | NA · US |
| Facility Support Assembly 3 Part 2 approved primary SKU | Kinetic Thermal | $211.9k | 15 weeks | EMEA · AE | |
| Facility Support Assembly 3 Part 2 approved alternate SKU | Apex Power Systems | $239.3k | 16 weeks | APAC · AU |
| Facility Support Assembly 3 Part 3 approved primary SKU | Northstar Electrical | $202.8k | 17 weeks | NA · CA | |
| Facility Support Assembly 3 Part 3 approved alternate SKU | HelioCool | $230.2k | 18 weeks | EMEA · FR |
| Facility Support Assembly 3 Part 4 approved primary SKU | Vertex Modular | $208.9k | 19 weeks | APAC · AU | |
| Facility Support Assembly 3 Part 4 approved alternate SKU | OmniControls | $236.3k | 20 weeks | NA · US |
| Facility Support Assembly 3 Part 5 approved primary SKU | BlueRiver Fabrication | $215k | 21 weeks | EMEA · ES | |
| Facility Support Assembly 3 Part 5 approved alternate SKU | Atlas Switchgear | $227.1k | 22 weeks | APAC · AU |
| Facility Support Assembly 4 Part 1 approved primary SKU | Kinetic Thermal | $205.8k | 23 weeks | NA · CA | |
| Facility Support Assembly 4 Part 1 approved alternate SKU | Apex Power Systems | $233.2k | 24 weeks | EMEA · DE |
| Facility Support Assembly 4 Part 2 approved primary SKU | Northstar Electrical | $211.9k | 25 weeks | APAC · AU | |
| Facility Support Assembly 4 Part 2 approved alternate SKU | HelioCool | $239.3k | 8 weeks | NA · US |
| Facility Support Assembly 4 Part 3 approved primary SKU | Vertex Modular | $202.8k | 9 weeks | EMEA · IE | |
| Facility Support Assembly 4 Part 3 approved alternate SKU | OmniControls | $230.2k | 10 weeks | APAC · AU |
| Facility Support Assembly 4 Part 4 approved primary SKU | BlueRiver Fabrication | $208.9k | 11 weeks | NA · CA | |
| Facility Support Assembly 4 Part 4 approved alternate SKU | Atlas Switchgear | $236.3k | 12 weeks | EMEA · GB |
| Facility Support Assembly 4 Part 5 approved primary SKU | Kinetic Thermal | $215k | 13 weeks | APAC · AU | |
| Facility Support Assembly 4 Part 5 approved alternate SKU | Apex Power Systems | $227.1k | 14 weeks | NA · US |
| Facility Support Assembly 5 Part 1 approved primary SKU | Northstar Electrical | $205.8k | 15 weeks | EMEA · NL | |
| Facility Support Assembly 5 Part 1 approved alternate SKU | HelioCool | $233.2k | 16 weeks | APAC · AU |
| Facility Support Assembly 5 Part 2 approved primary SKU | Vertex Modular | $211.9k | 17 weeks | NA · CA | |
| Facility Support Assembly 5 Part 2 approved alternate SKU | OmniControls | $239.3k | 18 weeks | EMEA · AE |
| Facility Support Assembly 5 Part 3 approved primary SKU | BlueRiver Fabrication | $202.8k | 19 weeks | APAC · AU | |
| Facility Support Assembly 5 Part 3 approved alternate SKU | Atlas Switchgear | $230.2k | 20 weeks | NA · US |
| Facility Support Assembly 5 Part 4 approved primary SKU | Kinetic Thermal | $208.9k | 21 weeks | EMEA · FR | |
| Facility Support Assembly 5 Part 4 approved alternate SKU | Apex Power Systems | $236.3k | 22 weeks | APAC · AU |
| Facility Support Assembly 5 Part 5 approved primary SKU | Northstar Electrical | $215k | 23 weeks | NA · CA | |
| Facility Support Assembly 5 Part 5 approved alternate SKU | HelioCool | $227.1k | 24 weeks | EMEA · ES |
| Fire and Life Safety Assembly 1 Part 1 approved primary SKU | Kinetic Thermal | $227.8k | 17 weeks | NA · CA | |
| Fire and Life Safety Assembly 1 Part 1 approved alternate SKU | Apex Power Systems | $258.1k | 18 weeks | EMEA · FR |
| Fire and Life Safety Assembly 1 Part 2 approved primary SKU | Northstar Electrical | $234.5k | 19 weeks | APAC · AU | |
| Fire and Life Safety Assembly 1 Part 2 approved alternate SKU | HelioCool | $264.8k | 20 weeks | NA · US |
| Fire and Life Safety Assembly 1 Part 3 approved primary SKU | Vertex Modular | $224.4k | 21 weeks | EMEA · ES | |
| Fire and Life Safety Assembly 1 Part 3 approved alternate SKU | OmniControls | $254.7k | 22 weeks | APAC · AU |
| Fire and Life Safety Assembly 1 Part 4 approved primary SKU | BlueRiver Fabrication | $231.1k | 23 weeks | NA · CA | |
| Fire and Life Safety Assembly 1 Part 4 approved alternate SKU | Atlas Switchgear | $261.4k | 24 weeks | EMEA · DE |
| Fire and Life Safety Assembly 1 Part 5 approved primary SKU | Kinetic Thermal | $237.9k | 25 weeks | APAC · AU | |
| Fire and Life Safety Assembly 1 Part 5 approved alternate SKU | Apex Power Systems | $251.3k | 8 weeks | NA · US |
| Fire and Life Safety Assembly 2 Part 1 approved primary SKU | Northstar Electrical | $227.8k | 9 weeks | EMEA · IE | |
| Fire and Life Safety Assembly 2 Part 1 approved alternate SKU | HelioCool | $258.1k | 10 weeks | APAC · AU |
| Fire and Life Safety Assembly 2 Part 2 approved primary SKU | Vertex Modular | $234.5k | 11 weeks | NA · CA | |
| Fire and Life Safety Assembly 2 Part 2 approved alternate SKU | OmniControls | $264.8k | 12 weeks | EMEA · GB |
| Fire and Life Safety Assembly 2 Part 3 approved primary SKU | BlueRiver Fabrication | $224.4k | 13 weeks | APAC · AU | |
| Fire and Life Safety Assembly 2 Part 3 approved alternate SKU | Atlas Switchgear | $254.7k | 14 weeks | NA · US |
| Fire and Life Safety Assembly 2 Part 4 approved primary SKU | Kinetic Thermal | $231.1k | 15 weeks | EMEA · NL | |
| Fire and Life Safety Assembly 2 Part 4 approved alternate SKU | Apex Power Systems | $261.4k | 16 weeks | APAC · AU |
| Fire and Life Safety Assembly 2 Part 5 approved primary SKU | Northstar Electrical | $237.9k | 17 weeks | NA · CA | |
| Fire and Life Safety Assembly 2 Part 5 approved alternate SKU | HelioCool | $251.3k | 18 weeks | EMEA · AE |
| Fire and Life Safety Assembly 3 Part 1 approved primary SKU | Vertex Modular | $227.8k | 19 weeks | APAC · AU | |
| Fire and Life Safety Assembly 3 Part 1 approved alternate SKU | OmniControls | $258.1k | 20 weeks | NA · US |
| Fire and Life Safety Assembly 3 Part 2 approved primary SKU | BlueRiver Fabrication | $234.5k | 21 weeks | EMEA · FR | |
| Fire and Life Safety Assembly 3 Part 2 approved alternate SKU | Atlas Switchgear | $264.8k | 22 weeks | APAC · AU |
| Fire and Life Safety Assembly 3 Part 3 approved primary SKU | Kinetic Thermal | $224.4k | 23 weeks | NA · CA | |
| Fire and Life Safety Assembly 3 Part 3 approved alternate SKU | Apex Power Systems | $254.7k | 24 weeks | EMEA · ES |
| Fire and Life Safety Assembly 3 Part 4 approved primary SKU | Northstar Electrical | $231.1k | 25 weeks | APAC · AU | |
| Fire and Life Safety Assembly 3 Part 4 approved alternate SKU | HelioCool | $261.4k | 8 weeks | NA · US |
| Fire and Life Safety Assembly 3 Part 5 approved primary SKU | Vertex Modular | $237.9k | 9 weeks | EMEA · DE | |
| Fire and Life Safety Assembly 3 Part 5 approved alternate SKU | OmniControls | $251.3k | 10 weeks | APAC · AU |
| Fire and Life Safety Assembly 4 Part 1 approved primary SKU | BlueRiver Fabrication | $227.8k | 11 weeks | NA · CA | |
| Fire and Life Safety Assembly 4 Part 1 approved alternate SKU | Atlas Switchgear | $258.1k | 12 weeks | EMEA · IE |
| Fire and Life Safety Assembly 4 Part 2 approved primary SKU | Kinetic Thermal | $234.5k | 13 weeks | APAC · AU | |
| Fire and Life Safety Assembly 4 Part 2 approved alternate SKU | Apex Power Systems | $264.8k | 14 weeks | NA · US |
| Fire and Life Safety Assembly 4 Part 3 approved primary SKU | Northstar Electrical | $224.4k | 15 weeks | EMEA · GB | |
| Fire and Life Safety Assembly 4 Part 3 approved alternate SKU | HelioCool | $254.7k | 16 weeks | APAC · AU |
| Fire and Life Safety Assembly 4 Part 4 approved primary SKU | Vertex Modular | $231.1k | 17 weeks | NA · CA | |
| Fire and Life Safety Assembly 4 Part 4 approved alternate SKU | OmniControls | $261.4k | 18 weeks | EMEA · NL |
| Fire and Life Safety Assembly 4 Part 5 approved primary SKU | BlueRiver Fabrication | $237.9k | 19 weeks | APAC · AU | |
| Fire and Life Safety Assembly 4 Part 5 approved alternate SKU | Atlas Switchgear | $251.3k | 20 weeks | NA · US |
| Fire and Life Safety Assembly 5 Part 1 approved primary SKU | Kinetic Thermal | $227.8k | 21 weeks | EMEA · AE | |
| Fire and Life Safety Assembly 5 Part 1 approved alternate SKU | Apex Power Systems | $258.1k | 22 weeks | APAC · AU |
| Fire and Life Safety Assembly 5 Part 2 approved primary SKU | Northstar Electrical | $234.5k | 23 weeks | NA · CA | |
| Fire and Life Safety Assembly 5 Part 2 approved alternate SKU | HelioCool | $264.8k | 24 weeks | EMEA · FR |
| Fire and Life Safety Assembly 5 Part 3 approved primary SKU | Vertex Modular | $224.4k | 25 weeks | APAC · AU | |
| Fire and Life Safety Assembly 5 Part 3 approved alternate SKU | OmniControls | $254.7k | 8 weeks | NA · US |
| Fire and Life Safety Assembly 5 Part 4 approved primary SKU | BlueRiver Fabrication | $231.1k | 9 weeks | EMEA · ES | |
| Fire and Life Safety Assembly 5 Part 4 approved alternate SKU | Atlas Switchgear | $261.4k | 10 weeks | APAC · AU |
| Fire and Life Safety Assembly 5 Part 5 approved primary SKU | Kinetic Thermal | $237.9k | 11 weeks | NA · CA | |
| Fire and Life Safety Assembly 5 Part 5 approved alternate SKU | Apex Power Systems | $251.3k | 12 weeks | EMEA · DE |
| FLEX Cooling Generation Assembly 1 Part 1 approved primary SKU | BlueRiver Fabrication | $251.7k | 25 weeks | APAC · AU | |
| FLEX Cooling Generation Assembly 1 Part 1 approved alternate SKU | Atlas Switchgear | $284.2k | 8 weeks | NA · US |
| FLEX Cooling Generation Assembly 1 Part 2 approved primary SKU | Kinetic Thermal | $240.8k | 9 weeks | EMEA · FR | |
| FLEX Cooling Generation Assembly 1 Part 2 approved alternate SKU | Apex Power Systems | $273.3k | 10 weeks | APAC · AU |
| FLEX Cooling Generation Assembly 2 Part 1 approved primary SKU | Northstar Electrical | $248.1k | 11 weeks | NA · CA | |
| FLEX Cooling Generation Assembly 2 Part 1 approved alternate SKU | HelioCool | $280.6k | 12 weeks | EMEA · ES |
| FLEX Cooling Generation Assembly 2 Part 2 approved primary SKU | Vertex Modular | $255.3k | 13 weeks | APAC · AU | |
| FLEX Cooling Generation Assembly 2 Part 2 approved alternate SKU | OmniControls | $269.7k | 14 weeks | NA · US |
| FLEX Cooling Generation Assembly 3 Part 1 approved primary SKU | BlueRiver Fabrication | $244.4k | 15 weeks | EMEA · DE | |
| FLEX Cooling Generation Assembly 3 Part 1 approved alternate SKU | Atlas Switchgear | $277k | 16 weeks | APAC · AU |
| FLEX Cooling Generation Assembly 3 Part 2 approved primary SKU | Kinetic Thermal | $251.7k | 17 weeks | NA · CA | |
| FLEX Cooling Generation Assembly 3 Part 2 approved alternate SKU | Apex Power Systems | $284.2k | 18 weeks | EMEA · IE |
| FLEX Heat Rejection Assembly 1 Part 1 approved primary SKU | Northstar Electrical | $75k | 19 weeks | APAC · AU | |
| FLEX Heat Rejection Assembly 1 Part 1 approved alternate SKU | HelioCool | $85.1k | 20 weeks | NA · US | |
| FLEX Heat Rejection Assembly 1 Part 1 approved alternate SKU | Vertex Modular | $95.3k | 21 weeks | EMEA · GB | |
| FLEX Heat Rejection Assembly 1 Part 1 approved alternate SKU | OmniControls | $105.4k | 22 weeks | APAC · AU |
| FLEX Heat Rejection Assembly 1 Part 2 approved primary SKU | BlueRiver Fabrication | $79.5k | 23 weeks | NA · CA | |
| FLEX Heat Rejection Assembly 1 Part 2 approved alternate SKU | Atlas Switchgear | $84k | 24 weeks | EMEA · NL | |
| FLEX Heat Rejection Assembly 1 Part 2 approved alternate SKU | Kinetic Thermal | $94.1k | 25 weeks | APAC · AU | |
| FLEX Heat Rejection Assembly 1 Part 2 approved alternate SKU | Apex Power Systems | $104.3k | 8 weeks | NA · US |
| FLEX Heat Rejection Assembly 1 Part 3 approved primary SKU | Northstar Electrical | $78.4k | 9 weeks | EMEA · AE | |
| FLEX Heat Rejection Assembly 1 Part 3 approved alternate SKU | HelioCool | $88.5k | 10 weeks | APAC · AU | |
| FLEX Heat Rejection Assembly 1 Part 3 approved alternate SKU | Vertex Modular | $93k | 11 weeks | NA · CA | |
| FLEX Heat Rejection Assembly 1 Part 3 approved alternate SKU | OmniControls | $103.1k | 12 weeks | EMEA · FR |
| FLEX Heat Rejection Assembly 1 Part 4 approved primary SKU | BlueRiver Fabrication | $77.3k | 13 weeks | APAC · AU | |
| FLEX Heat Rejection Assembly 1 Part 4 approved alternate SKU | Atlas Switchgear | $87.4k | 14 weeks | NA · US | |
| FLEX Heat Rejection Assembly 1 Part 4 approved alternate SKU | Kinetic Thermal | $97.5k | 15 weeks | EMEA · ES | |
| FLEX Heat Rejection Assembly 1 Part 4 approved alternate SKU | Apex Power Systems | $102k | 16 weeks | APAC · AU |
| FLEX Heat Rejection Assembly 2 Part 1 approved primary SKU | Northstar Electrical | $76.1k | 17 weeks | NA · CA | |
| FLEX Heat Rejection Assembly 2 Part 1 approved alternate SKU | HelioCool | $86.3k | 18 weeks | EMEA · DE | |
| FLEX Heat Rejection Assembly 2 Part 1 approved alternate SKU | Vertex Modular | $96.4k | 19 weeks | APAC · AU | |
| FLEX Heat Rejection Assembly 2 Part 1 approved alternate SKU | OmniControls | $106.5k | 20 weeks | NA · US |
| FLEX Heat Rejection Assembly 2 Part 2 approved primary SKU | BlueRiver Fabrication | $75k | 21 weeks | EMEA · IE | |
| FLEX Heat Rejection Assembly 2 Part 2 approved alternate SKU | Atlas Switchgear | $85.1k | 22 weeks | APAC · AU | |
| FLEX Heat Rejection Assembly 2 Part 2 approved alternate SKU | Kinetic Thermal | $95.3k | 23 weeks | NA · CA | |
| FLEX Heat Rejection Assembly 2 Part 2 approved alternate SKU | Apex Power Systems | $105.4k | 24 weeks | EMEA · GB |
| FLEX Heat Rejection Assembly 2 Part 3 approved primary SKU | Northstar Electrical | $79.5k | 25 weeks | APAC · AU | |
| FLEX Heat Rejection Assembly 2 Part 3 approved alternate SKU | HelioCool | $84k | 8 weeks | NA · US | |
| FLEX Heat Rejection Assembly 2 Part 3 approved alternate SKU | Vertex Modular | $94.1k | 9 weeks | EMEA · NL | |
| FLEX Heat Rejection Assembly 2 Part 3 approved alternate SKU | OmniControls | $104.3k | 10 weeks | APAC · AU |
| FLEX Heat Rejection Assembly 2 Part 4 approved primary SKU | BlueRiver Fabrication | $78.4k | 11 weeks | NA · CA | |
| FLEX Heat Rejection Assembly 2 Part 4 approved alternate SKU | Atlas Switchgear | $88.5k | 12 weeks | EMEA · AE | |
| FLEX Heat Rejection Assembly 2 Part 4 approved alternate SKU | Kinetic Thermal | $93k | 13 weeks | APAC · AU | |
| FLEX Heat Rejection Assembly 2 Part 4 approved alternate SKU | Apex Power Systems | $103.1k | 14 weeks | NA · US |
| FLEX Heat Rejection Assembly 3 Part 1 approved primary SKU | Northstar Electrical | $77.3k | 15 weeks | EMEA · FR | |
| FLEX Heat Rejection Assembly 3 Part 1 approved alternate SKU | HelioCool | $87.4k | 16 weeks | APAC · AU | |
| FLEX Heat Rejection Assembly 3 Part 1 approved alternate SKU | Vertex Modular | $97.5k | 17 weeks | NA · CA | |
| FLEX Heat Rejection Assembly 3 Part 1 approved alternate SKU | OmniControls | $102k | 18 weeks | EMEA · ES |
| FLEX Heat Rejection Assembly 3 Part 2 approved primary SKU | BlueRiver Fabrication | $76.1k | 19 weeks | APAC · AU | |
| FLEX Heat Rejection Assembly 3 Part 2 approved alternate SKU | Atlas Switchgear | $86.3k | 20 weeks | NA · US | |
| FLEX Heat Rejection Assembly 3 Part 2 approved alternate SKU | Kinetic Thermal | $96.4k | 21 weeks | EMEA · DE | |
| FLEX Heat Rejection Assembly 3 Part 2 approved alternate SKU | Apex Power Systems | $106.5k | 22 weeks | APAC · AU |
| FLEX Heat Rejection Assembly 3 Part 3 approved primary SKU | Northstar Electrical | $75k | 23 weeks | NA · CA | |
| FLEX Heat Rejection Assembly 3 Part 3 approved alternate SKU | HelioCool | $85.1k | 24 weeks | EMEA · IE | |
| FLEX Heat Rejection Assembly 3 Part 3 approved alternate SKU | Vertex Modular | $95.3k | 25 weeks | APAC · AU | |
| FLEX Heat Rejection Assembly 3 Part 3 approved alternate SKU | OmniControls | $105.4k | 8 weeks | NA · US |
| FLEX Heat Rejection Assembly 3 Part 4 approved primary SKU | BlueRiver Fabrication | $79.5k | 9 weeks | EMEA · GB | |
| FLEX Heat Rejection Assembly 3 Part 4 approved alternate SKU | Atlas Switchgear | $84k | 10 weeks | APAC · AU | |
| FLEX Heat Rejection Assembly 3 Part 4 approved alternate SKU | Kinetic Thermal | $94.1k | 11 weeks | NA · CA | |
| FLEX Heat Rejection Assembly 3 Part 4 approved alternate SKU | Apex Power Systems | $104.3k | 12 weeks | EMEA · NL |
| FLEX Heat Rejection Assembly 4 Part 1 approved primary SKU | Northstar Electrical | $78.4k | 13 weeks | APAC · AU | |
| FLEX Heat Rejection Assembly 4 Part 1 approved alternate SKU | HelioCool | $88.5k | 14 weeks | NA · US | |
| FLEX Heat Rejection Assembly 4 Part 1 approved alternate SKU | Vertex Modular | $93k | 15 weeks | EMEA · AE | |
| FLEX Heat Rejection Assembly 4 Part 1 approved alternate SKU | OmniControls | $103.1k | 16 weeks | APAC · AU |
| FLEX Heat Rejection Assembly 4 Part 2 approved primary SKU | BlueRiver Fabrication | $77.3k | 17 weeks | NA · CA | |
| FLEX Heat Rejection Assembly 4 Part 2 approved alternate SKU | Atlas Switchgear | $87.4k | 18 weeks | EMEA · FR | |
| FLEX Heat Rejection Assembly 4 Part 2 approved alternate SKU | Kinetic Thermal | $97.5k | 19 weeks | APAC · AU | |
| FLEX Heat Rejection Assembly 4 Part 2 approved alternate SKU | Apex Power Systems | $102k | 20 weeks | NA · US |
| FLEX Heat Rejection Assembly 4 Part 3 approved primary SKU | Northstar Electrical | $76.1k | 21 weeks | EMEA · ES | |
| FLEX Heat Rejection Assembly 4 Part 3 approved alternate SKU | HelioCool | $86.3k | 22 weeks | APAC · AU | |
| FLEX Heat Rejection Assembly 4 Part 3 approved alternate SKU | Vertex Modular | $96.4k | 23 weeks | NA · CA | |
| FLEX Heat Rejection Assembly 4 Part 3 approved alternate SKU | OmniControls | $106.5k | 24 weeks | EMEA · DE |
| FLEX Heat Rejection Assembly 4 Part 4 approved primary SKU | BlueRiver Fabrication | $75k | 25 weeks | APAC · AU | |
| FLEX Heat Rejection Assembly 4 Part 4 approved alternate SKU | Atlas Switchgear | $85.1k | 8 weeks | NA · US | |
| FLEX Heat Rejection Assembly 4 Part 4 approved alternate SKU | Kinetic Thermal | $95.3k | 9 weeks | EMEA · IE | |
| FLEX Heat Rejection Assembly 4 Part 4 approved alternate SKU | Apex Power Systems | $105.4k | 10 weeks | APAC · AU |
| FLEX Heat Rejection Assembly 5 Part 1 approved primary SKU | Northstar Electrical | $79.5k | 11 weeks | NA · CA | |
| FLEX Heat Rejection Assembly 5 Part 1 approved alternate SKU | HelioCool | $84k | 12 weeks | EMEA · GB | |
| FLEX Heat Rejection Assembly 5 Part 1 approved alternate SKU | Vertex Modular | $94.1k | 13 weeks | APAC · AU | |
| FLEX Heat Rejection Assembly 5 Part 1 approved alternate SKU | OmniControls | $104.3k | 14 weeks | NA · US |
| FLEX Heat Rejection Assembly 5 Part 2 approved primary SKU | BlueRiver Fabrication | $78.4k | 15 weeks | EMEA · NL | |
| FLEX Heat Rejection Assembly 5 Part 2 approved alternate SKU | Atlas Switchgear | $88.5k | 16 weeks | APAC · AU | |
| FLEX Heat Rejection Assembly 5 Part 2 approved alternate SKU | Kinetic Thermal | $93k | 17 weeks | NA · CA | |
| FLEX Heat Rejection Assembly 5 Part 2 approved alternate SKU | Apex Power Systems | $103.1k | 18 weeks | EMEA · AE |
| FLEX Heat Rejection Assembly 5 Part 3 approved primary SKU | Northstar Electrical | $77.3k | 19 weeks | APAC · AU | |
| FLEX Heat Rejection Assembly 5 Part 3 approved alternate SKU | HelioCool | $87.4k | 20 weeks | NA · US | |
| FLEX Heat Rejection Assembly 5 Part 3 approved alternate SKU | Vertex Modular | $97.5k | 21 weeks | EMEA · FR | |
| FLEX Heat Rejection Assembly 5 Part 3 approved alternate SKU | OmniControls | $102k | 22 weeks | APAC · AU |
| FLEX Heat Rejection Assembly 5 Part 4 approved primary SKU | BlueRiver Fabrication | $76.1k | 23 weeks | NA · CA | |
| FLEX Heat Rejection Assembly 5 Part 4 approved alternate SKU | Atlas Switchgear | $86.3k | 24 weeks | EMEA · ES | |
| FLEX Heat Rejection Assembly 5 Part 4 approved alternate SKU | Kinetic Thermal | $96.4k | 25 weeks | APAC · AU | |
| FLEX Heat Rejection Assembly 5 Part 4 approved alternate SKU | Apex Power Systems | $106.5k | 8 weeks | NA · US |
| FLEX Logistics Yard Assembly 1 Part 1 approved primary SKU | BlueRiver Fabrication | $276.4k | 21 weeks | EMEA · AE | |
| FLEX Logistics Yard Assembly 1 Part 1 approved alternate SKU | Atlas Switchgear | $312.6k | 22 weeks | APAC · AU |
| FLEX Logistics Yard Assembly 1 Part 2 approved primary SKU | Kinetic Thermal | $284.4k | 23 weeks | NA · CA | |
| FLEX Logistics Yard Assembly 1 Part 2 approved alternate SKU | Apex Power Systems | $300.5k | 24 weeks | EMEA · FR |
| FLEX Logistics Yard Assembly 2 Part 1 approved primary SKU | Northstar Electrical | $272.4k | 25 weeks | APAC · AU | |
| FLEX Logistics Yard Assembly 2 Part 1 approved alternate SKU | HelioCool | $308.6k | 8 weeks | NA · US |
| FLEX Logistics Yard Assembly 2 Part 2 approved primary SKU | Vertex Modular | $280.4k | 9 weeks | EMEA · ES | |
| FLEX Logistics Yard Assembly 2 Part 2 approved alternate SKU | OmniControls | $316.6k | 10 weeks | APAC · AU |
| FLEX Logistics Yard Assembly 3 Part 1 approved primary SKU | BlueRiver Fabrication | $268.3k | 11 weeks | NA · CA | |
| FLEX Logistics Yard Assembly 3 Part 1 approved alternate SKU | Atlas Switchgear | $304.6k | 12 weeks | EMEA · DE |
| FLEX Logistics Yard Assembly 3 Part 2 approved primary SKU | Kinetic Thermal | $276.4k | 13 weeks | APAC · AU | |
| FLEX Logistics Yard Assembly 3 Part 2 approved alternate SKU | Apex Power Systems | $312.6k | 14 weeks | NA · US |
| FLEX Server Hall Assembly 1 Part 1 approved primary SKU | Northstar Electrical | $259.2k | 9 weeks | EMEA · DE | |
| FLEX Server Hall Assembly 1 Part 1 approved alternate SKU | HelioCool | $294.2k | 10 weeks | APAC · AU |
| FLEX Server Hall Assembly 1 Part 2 approved primary SKU | Vertex Modular | $266.9k | 11 weeks | NA · CA | |
| FLEX Server Hall Assembly 1 Part 2 approved alternate SKU | OmniControls | $301.9k | 12 weeks | EMEA · IE |
| FLEX Server Hall Assembly 2 Part 1 approved primary SKU | BlueRiver Fabrication | $274.7k | 13 weeks | APAC · AU | |
| FLEX Server Hall Assembly 2 Part 1 approved alternate SKU | Atlas Switchgear | $290.3k | 14 weeks | NA · US |
| FLEX Server Hall Assembly 2 Part 2 approved primary SKU | Kinetic Thermal | $263.1k | 15 weeks | EMEA · GB | |
| FLEX Server Hall Assembly 2 Part 2 approved alternate SKU | Apex Power Systems | $298k | 16 weeks | APAC · AU |
| FLEX Server Hall Assembly 3 Part 1 approved primary SKU | Northstar Electrical | $270.8k | 17 weeks | NA · CA | |
| FLEX Server Hall Assembly 3 Part 1 approved alternate SKU | HelioCool | $305.8k | 18 weeks | EMEA · NL |
| FLEX Server Hall Assembly 3 Part 2 approved primary SKU | Vertex Modular | $259.2k | 19 weeks | APAC · AU | |
| FLEX Server Hall Assembly 3 Part 2 approved alternate SKU | OmniControls | $294.2k | 20 weeks | NA · US |
| FLEX UPS Assembly 1 Part 1 approved primary SKU | Northstar Electrical | $235.1k | 13 weeks | APAC · AU | |
| FLEX UPS Assembly 1 Part 1 approved alternate SKU | HelioCool | $266.4k | 14 weeks | NA · US |
| FLEX UPS Assembly 1 Part 2 approved primary SKU | Vertex Modular | $242.1k | 15 weeks | EMEA · IE | |
| FLEX UPS Assembly 1 Part 2 approved alternate SKU | OmniControls | $273.4k | 16 weeks | APAC · AU |
| FLEX UPS Assembly 2 Part 1 approved primary SKU | BlueRiver Fabrication | $231.7k | 17 weeks | NA · CA | |
| FLEX UPS Assembly 2 Part 1 approved alternate SKU | Atlas Switchgear | $262.9k | 18 weeks | EMEA · GB |
| FLEX UPS Assembly 2 Part 2 approved primary SKU | Kinetic Thermal | $238.6k | 19 weeks | APAC · AU | |
| FLEX UPS Assembly 2 Part 2 approved alternate SKU | Apex Power Systems | $269.9k | 20 weeks | NA · US |
| FLEX UPS Assembly 3 Part 1 approved primary SKU | Northstar Electrical | $245.6k | 21 weeks | EMEA · NL | |
| FLEX UPS Assembly 3 Part 1 approved alternate SKU | HelioCool | $259.5k | 22 weeks | APAC · AU |
| FLEX UPS Assembly 3 Part 2 approved primary SKU | Vertex Modular | $235.1k | 23 weeks | NA · CA | |
| FLEX UPS Assembly 3 Part 2 approved alternate SKU | OmniControls | $266.4k | 24 weeks | EMEA · AE |
| FLEX Water Treatment Assembly 1 Part 1 approved primary SKU | Northstar Electrical | $294.2k | 15 weeks | EMEA · IE | |
| FLEX Water Treatment Assembly 1 Part 1 approved alternate SKU | HelioCool | $310.8k | 16 weeks | APAC · AU |
| FLEX Water Treatment Assembly 1 Part 2 approved primary SKU | Vertex Modular | $281.7k | 17 weeks | NA · CA | |
| FLEX Water Treatment Assembly 1 Part 2 approved alternate SKU | OmniControls | $319.1k | 18 weeks | EMEA · GB |
| FLEX Water Treatment Assembly 2 Part 1 approved primary SKU | BlueRiver Fabrication | $290k | 19 weeks | APAC · AU | |
| FLEX Water Treatment Assembly 2 Part 1 approved alternate SKU | Atlas Switchgear | $327.5k | 20 weeks | NA · US |
| FLEX Water Treatment Assembly 2 Part 2 approved primary SKU | Kinetic Thermal | $277.5k | 21 weeks | EMEA · NL | |
| FLEX Water Treatment Assembly 2 Part 2 approved alternate SKU | Apex Power Systems | $315k | 22 weeks | APAC · AU |
| FLEX Water Treatment Assembly 3 Part 1 approved primary SKU | Northstar Electrical | $285.8k | 23 weeks | NA · CA | |
| FLEX Water Treatment Assembly 3 Part 1 approved alternate SKU | HelioCool | $323.3k | 24 weeks | EMEA · AE |
| FLEX Water Treatment Assembly 3 Part 2 approved primary SKU | Vertex Modular | $294.2k | 25 weeks | APAC · AU | |
| FLEX Water Treatment Assembly 3 Part 2 approved alternate SKU | OmniControls | $310.8k | 8 weeks | NA · US |
| FORGE AI Server Hall Assembly 1 Part 1 approved primary SKU | Northstar Electrical | $131.6k | 25 weeks | APAC · AU | |
| FORGE AI Server Hall Assembly 1 Part 1 approved alternate SKU | HelioCool | $148.8k | 8 weeks | NA · US | |
| FORGE AI Server Hall Assembly 1 Part 1 approved alternate SKU | Vertex Modular | $166.1k | 9 weeks | EMEA · IE | |
| FORGE AI Server Hall Assembly 1 Part 1 approved alternate SKU | OmniControls | $173.7k | 10 weeks | APAC · AU |
| FORGE AI Server Hall Assembly 1 Part 2 approved primary SKU | BlueRiver Fabrication | $129.7k | 11 weeks | NA · CA | |
| FORGE AI Server Hall Assembly 1 Part 2 approved alternate SKU | Atlas Switchgear | $146.9k | 12 weeks | EMEA · GB | |
| FORGE AI Server Hall Assembly 1 Part 2 approved alternate SKU | Kinetic Thermal | $164.2k | 13 weeks | APAC · AU | |
| FORGE AI Server Hall Assembly 1 Part 2 approved alternate SKU | Apex Power Systems | $181.4k | 14 weeks | NA · US |
| FORGE AI Server Hall Assembly 1 Part 3 approved primary SKU | Northstar Electrical | $127.8k | 15 weeks | EMEA · NL | |
| FORGE AI Server Hall Assembly 1 Part 3 approved alternate SKU | HelioCool | $145k | 16 weeks | APAC · AU | |
| FORGE AI Server Hall Assembly 1 Part 3 approved alternate SKU | Vertex Modular | $162.2k | 17 weeks | NA · CA | |
| FORGE AI Server Hall Assembly 1 Part 3 approved alternate SKU | OmniControls | $179.5k | 18 weeks | EMEA · AE |
| FORGE AI Server Hall Assembly 1 Part 4 approved primary SKU | BlueRiver Fabrication | $135.4k | 19 weeks | APAC · AU | |
| FORGE AI Server Hall Assembly 1 Part 4 approved alternate SKU | Atlas Switchgear | $143.1k | 20 weeks | NA · US | |
| FORGE AI Server Hall Assembly 1 Part 4 approved alternate SKU | Kinetic Thermal | $160.3k | 21 weeks | EMEA · FR | |
| FORGE AI Server Hall Assembly 1 Part 4 approved alternate SKU | Apex Power Systems | $177.6k | 22 weeks | APAC · AU |
| FORGE AI Server Hall Assembly 2 Part 1 approved primary SKU | Northstar Electrical | $133.5k | 23 weeks | NA · CA | |
| FORGE AI Server Hall Assembly 2 Part 1 approved alternate SKU | HelioCool | $150.7k | 24 weeks | EMEA · ES | |
| FORGE AI Server Hall Assembly 2 Part 1 approved alternate SKU | Vertex Modular | $158.4k | 25 weeks | APAC · AU | |
| FORGE AI Server Hall Assembly 2 Part 1 approved alternate SKU | OmniControls | $175.7k | 8 weeks | NA · US |
| FORGE AI Server Hall Assembly 2 Part 2 approved primary SKU | BlueRiver Fabrication | $131.6k | 9 weeks | EMEA · DE | |
| FORGE AI Server Hall Assembly 2 Part 2 approved alternate SKU | Atlas Switchgear | $148.8k | 10 weeks | APAC · AU | |
| FORGE AI Server Hall Assembly 2 Part 2 approved alternate SKU | Kinetic Thermal | $166.1k | 11 weeks | NA · CA | |
| FORGE AI Server Hall Assembly 2 Part 2 approved alternate SKU | Apex Power Systems | $173.7k | 12 weeks | EMEA · IE |
| FORGE AI Server Hall Assembly 2 Part 3 approved primary SKU | Northstar Electrical | $129.7k | 13 weeks | APAC · AU | |
| FORGE AI Server Hall Assembly 2 Part 3 approved alternate SKU | HelioCool | $146.9k | 14 weeks | NA · US | |
| FORGE AI Server Hall Assembly 2 Part 3 approved alternate SKU | Vertex Modular | $164.2k | 15 weeks | EMEA · GB | |
| FORGE AI Server Hall Assembly 2 Part 3 approved alternate SKU | OmniControls | $181.4k | 16 weeks | APAC · AU |
| FORGE AI Server Hall Assembly 2 Part 4 approved primary SKU | BlueRiver Fabrication | $127.8k | 17 weeks | NA · CA | |
| FORGE AI Server Hall Assembly 2 Part 4 approved alternate SKU | Atlas Switchgear | $145k | 18 weeks | EMEA · NL | |
| FORGE AI Server Hall Assembly 2 Part 4 approved alternate SKU | Kinetic Thermal | $162.2k | 19 weeks | APAC · AU | |
| FORGE AI Server Hall Assembly 2 Part 4 approved alternate SKU | Apex Power Systems | $179.5k | 20 weeks | NA · US |
| FORGE AI Server Hall Assembly 3 Part 1 approved primary SKU | Northstar Electrical | $135.4k | 21 weeks | EMEA · AE | |
| FORGE AI Server Hall Assembly 3 Part 1 approved alternate SKU | HelioCool | $143.1k | 22 weeks | APAC · AU | |
| FORGE AI Server Hall Assembly 3 Part 1 approved alternate SKU | Vertex Modular | $160.3k | 23 weeks | NA · CA | |
| FORGE AI Server Hall Assembly 3 Part 1 approved alternate SKU | OmniControls | $177.6k | 24 weeks | EMEA · FR |
| FORGE AI Server Hall Assembly 3 Part 2 approved primary SKU | BlueRiver Fabrication | $133.5k | 25 weeks | APAC · AU | |
| FORGE AI Server Hall Assembly 3 Part 2 approved alternate SKU | Atlas Switchgear | $150.7k | 8 weeks | NA · US | |
| FORGE AI Server Hall Assembly 3 Part 2 approved alternate SKU | Kinetic Thermal | $158.4k | 9 weeks | EMEA · ES | |
| FORGE AI Server Hall Assembly 3 Part 2 approved alternate SKU | Apex Power Systems | $175.7k | 10 weeks | APAC · AU |
| FORGE AI Server Hall Assembly 3 Part 3 approved primary SKU | Northstar Electrical | $131.6k | 11 weeks | NA · CA | |
| FORGE AI Server Hall Assembly 3 Part 3 approved alternate SKU | HelioCool | $148.8k | 12 weeks | EMEA · DE | |
| FORGE AI Server Hall Assembly 3 Part 3 approved alternate SKU | Vertex Modular | $166.1k | 13 weeks | APAC · AU | |
| FORGE AI Server Hall Assembly 3 Part 3 approved alternate SKU | OmniControls | $173.7k | 14 weeks | NA · US |
| FORGE AI Server Hall Assembly 3 Part 4 approved primary SKU | BlueRiver Fabrication | $129.7k | 15 weeks | EMEA · IE | |
| FORGE AI Server Hall Assembly 3 Part 4 approved alternate SKU | Atlas Switchgear | $146.9k | 16 weeks | APAC · AU | |
| FORGE AI Server Hall Assembly 3 Part 4 approved alternate SKU | Kinetic Thermal | $164.2k | 17 weeks | NA · CA | |
| FORGE AI Server Hall Assembly 3 Part 4 approved alternate SKU | Apex Power Systems | $181.4k | 18 weeks | EMEA · GB |
| FORGE AI Server Hall Assembly 4 Part 1 approved primary SKU | Northstar Electrical | $127.8k | 19 weeks | APAC · AU | |
| FORGE AI Server Hall Assembly 4 Part 1 approved alternate SKU | HelioCool | $145k | 20 weeks | NA · US | |
| FORGE AI Server Hall Assembly 4 Part 1 approved alternate SKU | Vertex Modular | $162.2k | 21 weeks | EMEA · NL | |
| FORGE AI Server Hall Assembly 4 Part 1 approved alternate SKU | OmniControls | $179.5k | 22 weeks | APAC · AU |
| FORGE AI Server Hall Assembly 4 Part 2 approved primary SKU | BlueRiver Fabrication | $135.4k | 23 weeks | NA · CA | |
| FORGE AI Server Hall Assembly 4 Part 2 approved alternate SKU | Atlas Switchgear | $143.1k | 24 weeks | EMEA · AE | |
| FORGE AI Server Hall Assembly 4 Part 2 approved alternate SKU | Kinetic Thermal | $160.3k | 25 weeks | APAC · AU | |
| FORGE AI Server Hall Assembly 4 Part 2 approved alternate SKU | Apex Power Systems | $177.6k | 8 weeks | NA · US |
| FORGE AI Server Hall Assembly 4 Part 3 approved primary SKU | Northstar Electrical | $133.5k | 9 weeks | EMEA · FR | |
| FORGE AI Server Hall Assembly 4 Part 3 approved alternate SKU | HelioCool | $150.7k | 10 weeks | APAC · AU | |
| FORGE AI Server Hall Assembly 4 Part 3 approved alternate SKU | Vertex Modular | $158.4k | 11 weeks | NA · CA | |
| FORGE AI Server Hall Assembly 4 Part 3 approved alternate SKU | OmniControls | $175.7k | 12 weeks | EMEA · ES |
| FORGE AI Server Hall Assembly 4 Part 4 approved primary SKU | BlueRiver Fabrication | $131.6k | 13 weeks | APAC · AU | |
| FORGE AI Server Hall Assembly 4 Part 4 approved alternate SKU | Atlas Switchgear | $148.8k | 14 weeks | NA · US | |
| FORGE AI Server Hall Assembly 4 Part 4 approved alternate SKU | Kinetic Thermal | $166.1k | 15 weeks | EMEA · DE | |
| FORGE AI Server Hall Assembly 4 Part 4 approved alternate SKU | Apex Power Systems | $173.7k | 16 weeks | APAC · AU |
| FORGE AI Server Hall Assembly 5 Part 1 approved primary SKU | Northstar Electrical | $129.7k | 17 weeks | NA · CA | |
| FORGE AI Server Hall Assembly 5 Part 1 approved alternate SKU | HelioCool | $146.9k | 18 weeks | EMEA · IE | |
| FORGE AI Server Hall Assembly 5 Part 1 approved alternate SKU | Vertex Modular | $164.2k | 19 weeks | APAC · AU | |
| FORGE AI Server Hall Assembly 5 Part 1 approved alternate SKU | OmniControls | $181.4k | 20 weeks | NA · US |
| FORGE AI Server Hall Assembly 5 Part 2 approved primary SKU | BlueRiver Fabrication | $127.8k | 21 weeks | EMEA · GB | |
| FORGE AI Server Hall Assembly 5 Part 2 approved alternate SKU | Atlas Switchgear | $145k | 22 weeks | APAC · AU | |
| FORGE AI Server Hall Assembly 5 Part 2 approved alternate SKU | Kinetic Thermal | $162.2k | 23 weeks | NA · CA | |
| FORGE AI Server Hall Assembly 5 Part 2 approved alternate SKU | Apex Power Systems | $179.5k | 24 weeks | EMEA · NL |
| FORGE AI Server Hall Assembly 5 Part 3 approved primary SKU | Northstar Electrical | $135.4k | 25 weeks | APAC · AU | |
| FORGE AI Server Hall Assembly 5 Part 3 approved alternate SKU | HelioCool | $143.1k | 8 weeks | NA · US | |
| FORGE AI Server Hall Assembly 5 Part 3 approved alternate SKU | Vertex Modular | $160.3k | 9 weeks | EMEA · AE | |
| FORGE AI Server Hall Assembly 5 Part 3 approved alternate SKU | OmniControls | $177.6k | 10 weeks | APAC · AU |
| FORGE AI Server Hall Assembly 5 Part 4 approved primary SKU | BlueRiver Fabrication | $133.5k | 11 weeks | NA · CA | |
| FORGE AI Server Hall Assembly 5 Part 4 approved alternate SKU | Atlas Switchgear | $150.7k | 12 weeks | EMEA · FR | |
| FORGE AI Server Hall Assembly 5 Part 4 approved alternate SKU | Kinetic Thermal | $158.4k | 13 weeks | APAC · AU | |
| FORGE AI Server Hall Assembly 5 Part 4 approved alternate SKU | Apex Power Systems | $175.7k | 14 weeks | NA · US |
| FORGE BESS Buffer Assembly 1 Part 1 approved primary SKU | Northstar Electrical | $134.9k | 15 weeks | EMEA · ES | |
| FORGE BESS Buffer Assembly 1 Part 1 approved alternate SKU | HelioCool | $152.6k | 16 weeks | APAC · AU | |
| FORGE BESS Buffer Assembly 1 Part 1 approved alternate SKU | Vertex Modular | $170.3k | 17 weeks | NA · CA | |
| FORGE BESS Buffer Assembly 1 Part 1 approved alternate SKU | OmniControls | $178.2k | 18 weeks | EMEA · DE |
| FORGE BESS Buffer Assembly 1 Part 2 approved primary SKU | BlueRiver Fabrication | $133k | 19 weeks | APAC · AU | |
| FORGE BESS Buffer Assembly 1 Part 2 approved alternate SKU | Atlas Switchgear | $150.7k | 20 weeks | NA · US | |
| FORGE BESS Buffer Assembly 1 Part 2 approved alternate SKU | Kinetic Thermal | $168.3k | 21 weeks | EMEA · IE | |
| FORGE BESS Buffer Assembly 1 Part 2 approved alternate SKU | Apex Power Systems | $186k | 22 weeks | APAC · AU |
| FORGE BESS Buffer Assembly 1 Part 3 approved primary SKU | Northstar Electrical | $131k | 23 weeks | NA · CA | |
| FORGE BESS Buffer Assembly 1 Part 3 approved alternate SKU | HelioCool | $148.7k | 24 weeks | EMEA · GB | |
| FORGE BESS Buffer Assembly 1 Part 3 approved alternate SKU | Vertex Modular | $166.4k | 25 weeks | APAC · AU | |
| FORGE BESS Buffer Assembly 1 Part 3 approved alternate SKU | OmniControls | $184.1k | 8 weeks | NA · US |
| FORGE BESS Buffer Assembly 1 Part 4 approved primary SKU | BlueRiver Fabrication | $138.9k | 9 weeks | EMEA · NL | |
| FORGE BESS Buffer Assembly 1 Part 4 approved alternate SKU | Atlas Switchgear | $146.7k | 10 weeks | APAC · AU | |
| FORGE BESS Buffer Assembly 1 Part 4 approved alternate SKU | Kinetic Thermal | $164.4k | 11 weeks | NA · CA | |
| FORGE BESS Buffer Assembly 1 Part 4 approved alternate SKU | Apex Power Systems | $182.1k | 12 weeks | EMEA · AE |
| FORGE BESS Buffer Assembly 2 Part 1 approved primary SKU | Northstar Electrical | $136.9k | 13 weeks | APAC · AU | |
| FORGE BESS Buffer Assembly 2 Part 1 approved alternate SKU | HelioCool | $154.6k | 14 weeks | NA · US | |
| FORGE BESS Buffer Assembly 2 Part 1 approved alternate SKU | Vertex Modular | $162.4k | 15 weeks | EMEA · FR | |
| FORGE BESS Buffer Assembly 2 Part 1 approved alternate SKU | OmniControls | $180.1k | 16 weeks | APAC · AU |
| FORGE BESS Buffer Assembly 2 Part 2 approved primary SKU | BlueRiver Fabrication | $134.9k | 17 weeks | NA · CA | |
| FORGE BESS Buffer Assembly 2 Part 2 approved alternate SKU | Atlas Switchgear | $152.6k | 18 weeks | EMEA · ES | |
| FORGE BESS Buffer Assembly 2 Part 2 approved alternate SKU | Kinetic Thermal | $170.3k | 19 weeks | APAC · AU | |
| FORGE BESS Buffer Assembly 2 Part 2 approved alternate SKU | Apex Power Systems | $178.2k | 20 weeks | NA · US |
| FORGE BESS Buffer Assembly 2 Part 3 approved primary SKU | Northstar Electrical | $133k | 21 weeks | EMEA · DE | |
| FORGE BESS Buffer Assembly 2 Part 3 approved alternate SKU | HelioCool | $150.7k | 22 weeks | APAC · AU | |
| FORGE BESS Buffer Assembly 2 Part 3 approved alternate SKU | Vertex Modular | $168.3k | 23 weeks | NA · CA | |
| FORGE BESS Buffer Assembly 2 Part 3 approved alternate SKU | OmniControls | $186k | 24 weeks | EMEA · IE |
| FORGE BESS Buffer Assembly 2 Part 4 approved primary SKU | BlueRiver Fabrication | $131k | 25 weeks | APAC · AU | |
| FORGE BESS Buffer Assembly 2 Part 4 approved alternate SKU | Atlas Switchgear | $148.7k | 8 weeks | NA · US | |
| FORGE BESS Buffer Assembly 2 Part 4 approved alternate SKU | Kinetic Thermal | $166.4k | 9 weeks | EMEA · GB | |
| FORGE BESS Buffer Assembly 2 Part 4 approved alternate SKU | Apex Power Systems | $184.1k | 10 weeks | APAC · AU |
| FORGE BESS Buffer Assembly 3 Part 1 approved primary SKU | Northstar Electrical | $138.9k | 11 weeks | NA · CA | |
| FORGE BESS Buffer Assembly 3 Part 1 approved alternate SKU | HelioCool | $146.7k | 12 weeks | EMEA · NL | |
| FORGE BESS Buffer Assembly 3 Part 1 approved alternate SKU | Vertex Modular | $164.4k | 13 weeks | APAC · AU | |
| FORGE BESS Buffer Assembly 3 Part 1 approved alternate SKU | OmniControls | $182.1k | 14 weeks | NA · US |
| FORGE BESS Buffer Assembly 3 Part 2 approved primary SKU | BlueRiver Fabrication | $136.9k | 15 weeks | EMEA · AE | |
| FORGE BESS Buffer Assembly 3 Part 2 approved alternate SKU | Atlas Switchgear | $154.6k | 16 weeks | APAC · AU | |
| FORGE BESS Buffer Assembly 3 Part 2 approved alternate SKU | Kinetic Thermal | $162.4k | 17 weeks | NA · CA | |
| FORGE BESS Buffer Assembly 3 Part 2 approved alternate SKU | Apex Power Systems | $180.1k | 18 weeks | EMEA · FR |
| FORGE BESS Buffer Assembly 3 Part 3 approved primary SKU | Northstar Electrical | $134.9k | 19 weeks | APAC · AU | |
| FORGE BESS Buffer Assembly 3 Part 3 approved alternate SKU | HelioCool | $152.6k | 20 weeks | NA · US | |
| FORGE BESS Buffer Assembly 3 Part 3 approved alternate SKU | Vertex Modular | $170.3k | 21 weeks | EMEA · ES | |
| FORGE BESS Buffer Assembly 3 Part 3 approved alternate SKU | OmniControls | $178.2k | 22 weeks | APAC · AU |
| FORGE BESS Buffer Assembly 3 Part 4 approved primary SKU | BlueRiver Fabrication | $133k | 23 weeks | NA · CA | |
| FORGE BESS Buffer Assembly 3 Part 4 approved alternate SKU | Atlas Switchgear | $150.7k | 24 weeks | EMEA · DE | |
| FORGE BESS Buffer Assembly 3 Part 4 approved alternate SKU | Kinetic Thermal | $168.3k | 25 weeks | APAC · AU | |
| FORGE BESS Buffer Assembly 3 Part 4 approved alternate SKU | Apex Power Systems | $186k | 8 weeks | NA · US |
| FORGE BESS Buffer Assembly 4 Part 1 approved primary SKU | Northstar Electrical | $131k | 9 weeks | EMEA · IE | |
| FORGE BESS Buffer Assembly 4 Part 1 approved alternate SKU | HelioCool | $148.7k | 10 weeks | APAC · AU | |
| FORGE BESS Buffer Assembly 4 Part 1 approved alternate SKU | Vertex Modular | $166.4k | 11 weeks | NA · CA | |
| FORGE BESS Buffer Assembly 4 Part 1 approved alternate SKU | OmniControls | $184.1k | 12 weeks | EMEA · GB |
| FORGE BESS Buffer Assembly 4 Part 2 approved primary SKU | BlueRiver Fabrication | $138.9k | 13 weeks | APAC · AU | |
| FORGE BESS Buffer Assembly 4 Part 2 approved alternate SKU | Atlas Switchgear | $146.7k | 14 weeks | NA · US | |
| FORGE BESS Buffer Assembly 4 Part 2 approved alternate SKU | Kinetic Thermal | $164.4k | 15 weeks | EMEA · NL | |
| FORGE BESS Buffer Assembly 4 Part 2 approved alternate SKU | Apex Power Systems | $182.1k | 16 weeks | APAC · AU |
| FORGE BESS Buffer Assembly 4 Part 3 approved primary SKU | Northstar Electrical | $136.9k | 17 weeks | NA · CA | |
| FORGE BESS Buffer Assembly 4 Part 3 approved alternate SKU | HelioCool | $154.6k | 18 weeks | EMEA · AE | |
| FORGE BESS Buffer Assembly 4 Part 3 approved alternate SKU | Vertex Modular | $162.4k | 19 weeks | APAC · AU | |
| FORGE BESS Buffer Assembly 4 Part 3 approved alternate SKU | OmniControls | $180.1k | 20 weeks | NA · US |
| FORGE BESS Buffer Assembly 4 Part 4 approved primary SKU | BlueRiver Fabrication | $134.9k | 21 weeks | EMEA · FR | |
| FORGE BESS Buffer Assembly 4 Part 4 approved alternate SKU | Atlas Switchgear | $152.6k | 22 weeks | APAC · AU | |
| FORGE BESS Buffer Assembly 4 Part 4 approved alternate SKU | Kinetic Thermal | $170.3k | 23 weeks | NA · CA | |
| FORGE BESS Buffer Assembly 4 Part 4 approved alternate SKU | Apex Power Systems | $178.2k | 24 weeks | EMEA · ES |
| FORGE BESS Buffer Assembly 5 Part 1 approved primary SKU | Northstar Electrical | $133k | 25 weeks | APAC · AU | |
| FORGE BESS Buffer Assembly 5 Part 1 approved alternate SKU | HelioCool | $150.7k | 8 weeks | NA · US | |
| FORGE BESS Buffer Assembly 5 Part 1 approved alternate SKU | Vertex Modular | $168.3k | 9 weeks | EMEA · DE | |
| FORGE BESS Buffer Assembly 5 Part 1 approved alternate SKU | OmniControls | $186k | 10 weeks | APAC · AU |
| FORGE BESS Buffer Assembly 5 Part 2 approved primary SKU | BlueRiver Fabrication | $131k | 11 weeks | NA · CA | |
| FORGE BESS Buffer Assembly 5 Part 2 approved alternate SKU | Atlas Switchgear | $148.7k | 12 weeks | EMEA · IE | |
| FORGE BESS Buffer Assembly 5 Part 2 approved alternate SKU | Kinetic Thermal | $166.4k | 13 weeks | APAC · AU | |
| FORGE BESS Buffer Assembly 5 Part 2 approved alternate SKU | Apex Power Systems | $184.1k | 14 weeks | NA · US |
| FORGE BESS Buffer Assembly 5 Part 3 approved primary SKU | Northstar Electrical | $138.9k | 15 weeks | EMEA · GB | |
| FORGE BESS Buffer Assembly 5 Part 3 approved alternate SKU | HelioCool | $146.7k | 16 weeks | APAC · AU | |
| FORGE BESS Buffer Assembly 5 Part 3 approved alternate SKU | Vertex Modular | $164.4k | 17 weeks | NA · CA | |
| FORGE BESS Buffer Assembly 5 Part 3 approved alternate SKU | OmniControls | $182.1k | 18 weeks | EMEA · NL |
| FORGE BESS Buffer Assembly 5 Part 4 approved primary SKU | BlueRiver Fabrication | $136.9k | 19 weeks | APAC · AU | |
| FORGE BESS Buffer Assembly 5 Part 4 approved alternate SKU | Atlas Switchgear | $154.6k | 20 weeks | NA · US | |
| FORGE BESS Buffer Assembly 5 Part 4 approved alternate SKU | Kinetic Thermal | $162.4k | 21 weeks | EMEA · AE | |
| FORGE BESS Buffer Assembly 5 Part 4 approved alternate SKU | Apex Power Systems | $180.1k | 22 weeks | APAC · AU |
| FORGE Heat Rejection Assembly 1 Part 1 approved primary SKU | Northstar Electrical | $128.2k | 17 weeks | NA · CA | |
| FORGE Heat Rejection Assembly 1 Part 1 approved alternate SKU | HelioCool | $145k | 18 weeks | EMEA · GB | |
| FORGE Heat Rejection Assembly 1 Part 1 approved alternate SKU | Vertex Modular | $161.9k | 19 weeks | APAC · AU | |
| FORGE Heat Rejection Assembly 1 Part 1 approved alternate SKU | OmniControls | $169.3k | 20 weeks | NA · US |
| FORGE Heat Rejection Assembly 1 Part 2 approved primary SKU | BlueRiver Fabrication | $126.4k | 21 weeks | EMEA · NL | |
| FORGE Heat Rejection Assembly 1 Part 2 approved alternate SKU | Atlas Switchgear | $143.2k | 22 weeks | APAC · AU | |
| FORGE Heat Rejection Assembly 1 Part 2 approved alternate SKU | Kinetic Thermal | $160k | 23 weeks | NA · CA | |
| FORGE Heat Rejection Assembly 1 Part 2 approved alternate SKU | Apex Power Systems | $176.8k | 24 weeks | EMEA · AE |
| FORGE Heat Rejection Assembly 1 Part 3 approved primary SKU | Northstar Electrical | $124.5k | 25 weeks | APAC · AU | |
| FORGE Heat Rejection Assembly 1 Part 3 approved alternate SKU | HelioCool | $141.3k | 8 weeks | NA · US | |
| FORGE Heat Rejection Assembly 1 Part 3 approved alternate SKU | Vertex Modular | $158.1k | 9 weeks | EMEA · FR | |
| FORGE Heat Rejection Assembly 1 Part 3 approved alternate SKU | OmniControls | $174.9k | 10 weeks | APAC · AU |
| FORGE Heat Rejection Assembly 1 Part 4 approved primary SKU | BlueRiver Fabrication | $132k | 11 weeks | NA · CA | |
| FORGE Heat Rejection Assembly 1 Part 4 approved alternate SKU | Atlas Switchgear | $139.4k | 12 weeks | EMEA · ES | |
| FORGE Heat Rejection Assembly 1 Part 4 approved alternate SKU | Kinetic Thermal | $156.2k | 13 weeks | APAC · AU | |
| FORGE Heat Rejection Assembly 1 Part 4 approved alternate SKU | Apex Power Systems | $173.1k | 14 weeks | NA · US |
| FORGE Heat Rejection Assembly 2 Part 1 approved primary SKU | Northstar Electrical | $130.1k | 15 weeks | EMEA · DE | |
| FORGE Heat Rejection Assembly 2 Part 1 approved alternate SKU | HelioCool | $146.9k | 16 weeks | APAC · AU | |
| FORGE Heat Rejection Assembly 2 Part 1 approved alternate SKU | Vertex Modular | $154.4k | 17 weeks | NA · CA | |
| FORGE Heat Rejection Assembly 2 Part 1 approved alternate SKU | OmniControls | $171.2k | 18 weeks | EMEA · IE |
| FORGE Heat Rejection Assembly 2 Part 2 approved primary SKU | BlueRiver Fabrication | $128.2k | 19 weeks | APAC · AU | |
| FORGE Heat Rejection Assembly 2 Part 2 approved alternate SKU | Atlas Switchgear | $145k | 20 weeks | NA · US | |
| FORGE Heat Rejection Assembly 2 Part 2 approved alternate SKU | Kinetic Thermal | $161.9k | 21 weeks | EMEA · GB | |
| FORGE Heat Rejection Assembly 2 Part 2 approved alternate SKU | Apex Power Systems | $169.3k | 22 weeks | APAC · AU |
| FORGE Heat Rejection Assembly 2 Part 3 approved primary SKU | Northstar Electrical | $126.4k | 23 weeks | NA · CA | |
| FORGE Heat Rejection Assembly 2 Part 3 approved alternate SKU | HelioCool | $143.2k | 24 weeks | EMEA · NL | |
| FORGE Heat Rejection Assembly 2 Part 3 approved alternate SKU | Vertex Modular | $160k | 25 weeks | APAC · AU | |
| FORGE Heat Rejection Assembly 2 Part 3 approved alternate SKU | OmniControls | $176.8k | 8 weeks | NA · US |
| FORGE Heat Rejection Assembly 2 Part 4 approved primary SKU | BlueRiver Fabrication | $124.5k | 9 weeks | EMEA · AE | |
| FORGE Heat Rejection Assembly 2 Part 4 approved alternate SKU | Atlas Switchgear | $141.3k | 10 weeks | APAC · AU | |
| FORGE Heat Rejection Assembly 2 Part 4 approved alternate SKU | Kinetic Thermal | $158.1k | 11 weeks | NA · CA | |
| FORGE Heat Rejection Assembly 2 Part 4 approved alternate SKU | Apex Power Systems | $174.9k | 12 weeks | EMEA · FR |
| FORGE Heat Rejection Assembly 3 Part 1 approved primary SKU | Northstar Electrical | $132k | 13 weeks | APAC · AU | |
| FORGE Heat Rejection Assembly 3 Part 1 approved alternate SKU | HelioCool | $139.4k | 14 weeks | NA · US | |
| FORGE Heat Rejection Assembly 3 Part 1 approved alternate SKU | Vertex Modular | $156.2k | 15 weeks | EMEA · ES | |
| FORGE Heat Rejection Assembly 3 Part 1 approved alternate SKU | OmniControls | $173.1k | 16 weeks | APAC · AU |
| FORGE Heat Rejection Assembly 3 Part 2 approved primary SKU | BlueRiver Fabrication | $130.1k | 17 weeks | NA · CA | |
| FORGE Heat Rejection Assembly 3 Part 2 approved alternate SKU | Atlas Switchgear | $146.9k | 18 weeks | EMEA · DE | |
| FORGE Heat Rejection Assembly 3 Part 2 approved alternate SKU | Kinetic Thermal | $154.4k | 19 weeks | APAC · AU | |
| FORGE Heat Rejection Assembly 3 Part 2 approved alternate SKU | Apex Power Systems | $171.2k | 20 weeks | NA · US |
| FORGE Heat Rejection Assembly 3 Part 3 approved primary SKU | Northstar Electrical | $128.2k | 21 weeks | EMEA · IE | |
| FORGE Heat Rejection Assembly 3 Part 3 approved alternate SKU | HelioCool | $145k | 22 weeks | APAC · AU | |
| FORGE Heat Rejection Assembly 3 Part 3 approved alternate SKU | Vertex Modular | $161.9k | 23 weeks | NA · CA | |
| FORGE Heat Rejection Assembly 3 Part 3 approved alternate SKU | OmniControls | $169.3k | 24 weeks | EMEA · GB |
| FORGE Heat Rejection Assembly 3 Part 4 approved primary SKU | BlueRiver Fabrication | $126.4k | 25 weeks | APAC · AU | |
| FORGE Heat Rejection Assembly 3 Part 4 approved alternate SKU | Atlas Switchgear | $143.2k | 8 weeks | NA · US | |
| FORGE Heat Rejection Assembly 3 Part 4 approved alternate SKU | Kinetic Thermal | $160k | 9 weeks | EMEA · NL | |
| FORGE Heat Rejection Assembly 3 Part 4 approved alternate SKU | Apex Power Systems | $176.8k | 10 weeks | APAC · AU |
| FORGE Heat Rejection Assembly 4 Part 1 approved primary SKU | Northstar Electrical | $124.5k | 11 weeks | NA · CA | |
| FORGE Heat Rejection Assembly 4 Part 1 approved alternate SKU | HelioCool | $141.3k | 12 weeks | EMEA · AE | |
| FORGE Heat Rejection Assembly 4 Part 1 approved alternate SKU | Vertex Modular | $158.1k | 13 weeks | APAC · AU | |
| FORGE Heat Rejection Assembly 4 Part 1 approved alternate SKU | OmniControls | $174.9k | 14 weeks | NA · US |
| FORGE Heat Rejection Assembly 4 Part 2 approved primary SKU | BlueRiver Fabrication | $132k | 15 weeks | EMEA · FR | |
| FORGE Heat Rejection Assembly 4 Part 2 approved alternate SKU | Atlas Switchgear | $139.4k | 16 weeks | APAC · AU | |
| FORGE Heat Rejection Assembly 4 Part 2 approved alternate SKU | Kinetic Thermal | $156.2k | 17 weeks | NA · CA | |
| FORGE Heat Rejection Assembly 4 Part 2 approved alternate SKU | Apex Power Systems | $173.1k | 18 weeks | EMEA · ES |
| FORGE Heat Rejection Assembly 4 Part 3 approved primary SKU | Northstar Electrical | $130.1k | 19 weeks | APAC · AU | |
| FORGE Heat Rejection Assembly 4 Part 3 approved alternate SKU | HelioCool | $146.9k | 20 weeks | NA · US | |
| FORGE Heat Rejection Assembly 4 Part 3 approved alternate SKU | Vertex Modular | $154.4k | 21 weeks | EMEA · DE | |
| FORGE Heat Rejection Assembly 4 Part 3 approved alternate SKU | OmniControls | $171.2k | 22 weeks | APAC · AU |
| FORGE Heat Rejection Assembly 4 Part 4 approved primary SKU | BlueRiver Fabrication | $128.2k | 23 weeks | NA · CA | |
| FORGE Heat Rejection Assembly 4 Part 4 approved alternate SKU | Atlas Switchgear | $145k | 24 weeks | EMEA · IE | |
| FORGE Heat Rejection Assembly 4 Part 4 approved alternate SKU | Kinetic Thermal | $161.9k | 25 weeks | APAC · AU | |
| FORGE Heat Rejection Assembly 4 Part 4 approved alternate SKU | Apex Power Systems | $169.3k | 8 weeks | NA · US |
| FORGE Heat Rejection Assembly 5 Part 1 approved primary SKU | Northstar Electrical | $126.4k | 9 weeks | EMEA · GB | |
| FORGE Heat Rejection Assembly 5 Part 1 approved alternate SKU | HelioCool | $143.2k | 10 weeks | APAC · AU | |
| FORGE Heat Rejection Assembly 5 Part 1 approved alternate SKU | Vertex Modular | $160k | 11 weeks | NA · CA | |
| FORGE Heat Rejection Assembly 5 Part 1 approved alternate SKU | OmniControls | $176.8k | 12 weeks | EMEA · NL |
| FORGE Heat Rejection Assembly 5 Part 2 approved primary SKU | BlueRiver Fabrication | $124.5k | 13 weeks | APAC · AU | |
| FORGE Heat Rejection Assembly 5 Part 2 approved alternate SKU | Atlas Switchgear | $141.3k | 14 weeks | NA · US | |
| FORGE Heat Rejection Assembly 5 Part 2 approved alternate SKU | Kinetic Thermal | $158.1k | 15 weeks | EMEA · AE | |
| FORGE Heat Rejection Assembly 5 Part 2 approved alternate SKU | Apex Power Systems | $174.9k | 16 weeks | APAC · AU |
| FORGE Heat Rejection Assembly 5 Part 3 approved primary SKU | Northstar Electrical | $132k | 17 weeks | NA · CA | |
| FORGE Heat Rejection Assembly 5 Part 3 approved alternate SKU | HelioCool | $139.4k | 18 weeks | EMEA · FR | |
| FORGE Heat Rejection Assembly 5 Part 3 approved alternate SKU | Vertex Modular | $156.2k | 19 weeks | APAC · AU | |
| FORGE Heat Rejection Assembly 5 Part 3 approved alternate SKU | OmniControls | $173.1k | 20 weeks | NA · US |
| FORGE Heat Rejection Assembly 5 Part 4 approved primary SKU | BlueRiver Fabrication | $130.1k | 21 weeks | EMEA · ES | |
| FORGE Heat Rejection Assembly 5 Part 4 approved alternate SKU | Atlas Switchgear | $146.9k | 22 weeks | APAC · AU | |
| FORGE Heat Rejection Assembly 5 Part 4 approved alternate SKU | Kinetic Thermal | $154.4k | 23 weeks | NA · CA | |
| FORGE Heat Rejection Assembly 5 Part 4 approved alternate SKU | Apex Power Systems | $171.2k | 24 weeks | EMEA · DE |
| FORGE High Density UPS Assembly 1 Part 1 approved primary SKU | BlueRiver Fabrication | $199.6k | 9 weeks | EMEA · FR | |
| FORGE High Density UPS Assembly 1 Part 1 approved alternate SKU | Atlas Switchgear | $226.2k | 10 weeks | APAC · AU | |
| FORGE High Density UPS Assembly 1 Part 1 approved alternate SKU | Kinetic Thermal | $252.7k | 11 weeks | NA · CA | |
| FORGE High Density UPS Assembly 1 Part 1 expedited cross-region alternate | BlueRiver Fabrication | $31k | 6 weeks | EMEA · DE |
| FORGE High Density UPS Assembly 1 Part 2 approved primary SKU | Apex Power Systems | $208.5k | 12 weeks | EMEA · ES | |
| FORGE High Density UPS Assembly 1 Part 2 approved alternate SKU | Northstar Electrical | $220.3k | 13 weeks | APAC · AU | |
| FORGE High Density UPS Assembly 1 Part 2 approved alternate SKU | HelioCool | $246.8k | 14 weeks | NA · US | |
| FORGE High Density UPS Assembly 1 Part 2 expedited cross-region alternate | Atlas Switchgear | $32.2k | 7 weeks | APAC · AU |
| FORGE High Density UPS Assembly 1 Part 3 approved primary SKU | Vertex Modular | $202.6k | 15 weeks | EMEA · DE | |
| FORGE High Density UPS Assembly 1 Part 3 approved alternate SKU | OmniControls | $229.1k | 16 weeks | APAC · AU | |
| FORGE High Density UPS Assembly 1 Part 3 approved alternate SKU | BlueRiver Fabrication | $255.7k | 17 weeks | NA · CA | |
| FORGE High Density UPS Assembly 1 Part 3 expedited cross-region alternate | Kinetic Thermal | $33.3k | 8 weeks | NA · CA |
| FORGE High Density UPS Assembly 2 Part 1 approved primary SKU | Atlas Switchgear | $196.7k | 18 weeks | EMEA · IE | |
| FORGE High Density UPS Assembly 2 Part 1 approved alternate SKU | Kinetic Thermal | $223.2k | 19 weeks | APAC · AU | |
| FORGE High Density UPS Assembly 2 Part 1 approved alternate SKU | Apex Power Systems | $249.8k | 20 weeks | NA · US | |
| FORGE High Density UPS Assembly 2 Part 1 expedited cross-region alternate | Apex Power Systems | $34.5k | 9 weeks | EMEA · IE |
| FORGE High Density UPS Assembly 2 Part 2 approved primary SKU | Northstar Electrical | $205.5k | 21 weeks | EMEA · GB | |
| FORGE High Density UPS Assembly 2 Part 2 approved alternate SKU | HelioCool | $232.1k | 22 weeks | APAC · AU | |
| FORGE High Density UPS Assembly 2 Part 2 approved alternate SKU | Vertex Modular | $243.9k | 23 weeks | NA · CA | |
| FORGE High Density UPS Assembly 2 Part 2 expedited cross-region alternate | Northstar Electrical | $35.6k | 10 weeks | APAC · AU |
| FORGE High Density UPS Assembly 2 Part 3 approved primary SKU | OmniControls | $199.6k | 24 weeks | EMEA · NL | |
| FORGE High Density UPS Assembly 2 Part 3 approved alternate SKU | BlueRiver Fabrication | $226.2k | 25 weeks | APAC · AU | |
| FORGE High Density UPS Assembly 2 Part 3 approved alternate SKU | Atlas Switchgear | $252.7k | 8 weeks | NA · US | |
| FORGE High Density UPS Assembly 2 Part 3 expedited cross-region alternate | HelioCool | $36.8k | 11 weeks | NA · US |
| FORGE High Density UPS Assembly 3 Part 1 approved primary SKU | Kinetic Thermal | $208.5k | 9 weeks | EMEA · AE | |
| FORGE High Density UPS Assembly 3 Part 1 approved alternate SKU | Apex Power Systems | $220.3k | 10 weeks | APAC · AU | |
| FORGE High Density UPS Assembly 3 Part 1 approved alternate SKU | Northstar Electrical | $246.8k | 11 weeks | NA · CA | |
| FORGE High Density UPS Assembly 3 Part 1 expedited cross-region alternate | Vertex Modular | $37.9k | 12 weeks | EMEA · GB |
| FORGE High Density UPS Assembly 3 Part 2 approved primary SKU | HelioCool | $202.6k | 12 weeks | EMEA · FR | |
| FORGE High Density UPS Assembly 3 Part 2 approved alternate SKU | Vertex Modular | $229.1k | 13 weeks | APAC · AU | |
| FORGE High Density UPS Assembly 3 Part 2 approved alternate SKU | OmniControls | $255.7k | 14 weeks | NA · US | |
| FORGE High Density UPS Assembly 3 Part 2 expedited cross-region alternate | OmniControls | $39.1k | 13 weeks | APAC · AU |
| FORGE High Density UPS Assembly 3 Part 3 approved primary SKU | BlueRiver Fabrication | $196.7k | 15 weeks | EMEA · ES | |
| FORGE High Density UPS Assembly 3 Part 3 approved alternate SKU | Atlas Switchgear | $223.2k | 16 weeks | APAC · AU | |
| FORGE High Density UPS Assembly 3 Part 3 approved alternate SKU | Kinetic Thermal | $249.8k | 17 weeks | NA · CA | |
| FORGE High Density UPS Assembly 3 Part 3 expedited cross-region alternate | BlueRiver Fabrication | $40.2k | 14 weeks | NA · CA |
| FORGE High Density UPS Assembly 4 Part 1 approved primary SKU | Apex Power Systems | $205.5k | 18 weeks | EMEA · DE | |
| FORGE High Density UPS Assembly 4 Part 1 approved alternate SKU | Northstar Electrical | $232.1k | 19 weeks | APAC · AU | |
| FORGE High Density UPS Assembly 4 Part 1 approved alternate SKU | HelioCool | $243.9k | 20 weeks | NA · US | |
| FORGE High Density UPS Assembly 4 Part 1 expedited cross-region alternate | Atlas Switchgear | $41.4k | 15 weeks | EMEA · NL |
| FORGE High Density UPS Assembly 4 Part 2 approved primary SKU | Vertex Modular | $199.6k | 21 weeks | EMEA · IE | |
| FORGE High Density UPS Assembly 4 Part 2 approved alternate SKU | OmniControls | $226.2k | 22 weeks | APAC · AU | |
| FORGE High Density UPS Assembly 4 Part 2 approved alternate SKU | BlueRiver Fabrication | $252.7k | 23 weeks | NA · CA | |
| FORGE High Density UPS Assembly 4 Part 2 expedited cross-region alternate | Kinetic Thermal | $42.5k | 16 weeks | APAC · AU |
| FORGE High Density UPS Assembly 4 Part 3 approved primary SKU | Atlas Switchgear | $208.5k | 24 weeks | EMEA · GB | |
| FORGE High Density UPS Assembly 4 Part 3 approved alternate SKU | Kinetic Thermal | $220.3k | 25 weeks | APAC · AU | |
| FORGE High Density UPS Assembly 4 Part 3 approved alternate SKU | Apex Power Systems | $246.8k | 8 weeks | NA · US | |
| FORGE High Density UPS Assembly 4 Part 3 expedited cross-region alternate | Apex Power Systems | $43.7k | 17 weeks | NA · US |
| FORGE Immersion Ready Interface Assembly 1 Part 1 approved primary SKU | Northstar Electrical | $138.3k | 23 weeks | NA · CA | |
| FORGE Immersion Ready Interface Assembly 1 Part 1 approved alternate SKU | HelioCool | $156.4k | 24 weeks | EMEA · FR | |
| FORGE Immersion Ready Interface Assembly 1 Part 1 approved alternate SKU | Vertex Modular | $174.5k | 25 weeks | APAC · AU | |
| FORGE Immersion Ready Interface Assembly 1 Part 1 approved alternate SKU | OmniControls | $182.6k | 8 weeks | NA · US |
| FORGE Immersion Ready Interface Assembly 1 Part 2 approved primary SKU | BlueRiver Fabrication | $136.3k | 9 weeks | EMEA · ES | |
| FORGE Immersion Ready Interface Assembly 1 Part 2 approved alternate SKU | Atlas Switchgear | $154.4k | 10 weeks | APAC · AU | |
| FORGE Immersion Ready Interface Assembly 1 Part 2 approved alternate SKU | Kinetic Thermal | $172.5k | 11 weeks | NA · CA | |
| FORGE Immersion Ready Interface Assembly 1 Part 2 approved alternate SKU | Apex Power Systems | $190.6k | 12 weeks | EMEA · DE |
| FORGE Immersion Ready Interface Assembly 1 Part 3 approved primary SKU | Northstar Electrical | $134.3k | 13 weeks | APAC · AU | |
| FORGE Immersion Ready Interface Assembly 1 Part 3 approved alternate SKU | HelioCool | $152.4k | 14 weeks | NA · US | |
| FORGE Immersion Ready Interface Assembly 1 Part 3 approved alternate SKU | Vertex Modular | $170.5k | 15 weeks | EMEA · IE | |
| FORGE Immersion Ready Interface Assembly 1 Part 3 approved alternate SKU | OmniControls | $188.6k | 16 weeks | APAC · AU |
| FORGE Immersion Ready Interface Assembly 1 Part 4 approved primary SKU | BlueRiver Fabrication | $142.3k | 17 weeks | NA · CA | |
| FORGE Immersion Ready Interface Assembly 1 Part 4 approved alternate SKU | Atlas Switchgear | $150.4k | 18 weeks | EMEA · GB | |
| FORGE Immersion Ready Interface Assembly 1 Part 4 approved alternate SKU | Kinetic Thermal | $168.5k | 19 weeks | APAC · AU | |
| FORGE Immersion Ready Interface Assembly 1 Part 4 approved alternate SKU | Apex Power Systems | $186.6k | 20 weeks | NA · US |
| FORGE Immersion Ready Interface Assembly 2 Part 1 approved primary SKU | Northstar Electrical | $140.3k | 21 weeks | EMEA · NL | |
| FORGE Immersion Ready Interface Assembly 2 Part 1 approved alternate SKU | HelioCool | $158.4k | 22 weeks | APAC · AU | |
| FORGE Immersion Ready Interface Assembly 2 Part 1 approved alternate SKU | Vertex Modular | $166.5k | 23 weeks | NA · CA | |
| FORGE Immersion Ready Interface Assembly 2 Part 1 approved alternate SKU | OmniControls | $184.6k | 24 weeks | EMEA · AE |
| FORGE Immersion Ready Interface Assembly 2 Part 2 approved primary SKU | BlueRiver Fabrication | $138.3k | 25 weeks | APAC · AU | |
| FORGE Immersion Ready Interface Assembly 2 Part 2 approved alternate SKU | Atlas Switchgear | $156.4k | 8 weeks | NA · US | |
| FORGE Immersion Ready Interface Assembly 2 Part 2 approved alternate SKU | Kinetic Thermal | $174.5k | 9 weeks | EMEA · FR | |
| FORGE Immersion Ready Interface Assembly 2 Part 2 approved alternate SKU | Apex Power Systems | $182.6k | 10 weeks | APAC · AU |
| FORGE Immersion Ready Interface Assembly 2 Part 3 approved primary SKU | Northstar Electrical | $136.3k | 11 weeks | NA · CA | |
| FORGE Immersion Ready Interface Assembly 2 Part 3 approved alternate SKU | HelioCool | $154.4k | 12 weeks | EMEA · ES | |
| FORGE Immersion Ready Interface Assembly 2 Part 3 approved alternate SKU | Vertex Modular | $172.5k | 13 weeks | APAC · AU | |
| FORGE Immersion Ready Interface Assembly 2 Part 3 approved alternate SKU | OmniControls | $190.6k | 14 weeks | NA · US |
| FORGE Immersion Ready Interface Assembly 2 Part 4 approved primary SKU | BlueRiver Fabrication | $134.3k | 15 weeks | EMEA · DE | |
| FORGE Immersion Ready Interface Assembly 2 Part 4 approved alternate SKU | Atlas Switchgear | $152.4k | 16 weeks | APAC · AU | |
| FORGE Immersion Ready Interface Assembly 2 Part 4 approved alternate SKU | Kinetic Thermal | $170.5k | 17 weeks | NA · CA | |
| FORGE Immersion Ready Interface Assembly 2 Part 4 approved alternate SKU | Apex Power Systems | $188.6k | 18 weeks | EMEA · IE |
| FORGE Immersion Ready Interface Assembly 3 Part 1 approved primary SKU | Northstar Electrical | $142.3k | 19 weeks | APAC · AU | |
| FORGE Immersion Ready Interface Assembly 3 Part 1 approved alternate SKU | HelioCool | $150.4k | 20 weeks | NA · US | |
| FORGE Immersion Ready Interface Assembly 3 Part 1 approved alternate SKU | Vertex Modular | $168.5k | 21 weeks | EMEA · GB | |
| FORGE Immersion Ready Interface Assembly 3 Part 1 approved alternate SKU | OmniControls | $186.6k | 22 weeks | APAC · AU |
| FORGE Immersion Ready Interface Assembly 3 Part 2 approved primary SKU | BlueRiver Fabrication | $140.3k | 23 weeks | NA · CA | |
| FORGE Immersion Ready Interface Assembly 3 Part 2 approved alternate SKU | Atlas Switchgear | $158.4k | 24 weeks | EMEA · NL | |
| FORGE Immersion Ready Interface Assembly 3 Part 2 approved alternate SKU | Kinetic Thermal | $166.5k | 25 weeks | APAC · AU | |
| FORGE Immersion Ready Interface Assembly 3 Part 2 approved alternate SKU | Apex Power Systems | $184.6k | 8 weeks | NA · US |
| FORGE Immersion Ready Interface Assembly 3 Part 3 approved primary SKU | Northstar Electrical | $138.3k | 9 weeks | EMEA · AE | |
| FORGE Immersion Ready Interface Assembly 3 Part 3 approved alternate SKU | HelioCool | $156.4k | 10 weeks | APAC · AU | |
| FORGE Immersion Ready Interface Assembly 3 Part 3 approved alternate SKU | Vertex Modular | $174.5k | 11 weeks | NA · CA | |
| FORGE Immersion Ready Interface Assembly 3 Part 3 approved alternate SKU | OmniControls | $182.6k | 12 weeks | EMEA · FR |
| FORGE Immersion Ready Interface Assembly 3 Part 4 approved primary SKU | BlueRiver Fabrication | $136.3k | 13 weeks | APAC · AU | |
| FORGE Immersion Ready Interface Assembly 3 Part 4 approved alternate SKU | Atlas Switchgear | $154.4k | 14 weeks | NA · US | |
| FORGE Immersion Ready Interface Assembly 3 Part 4 approved alternate SKU | Kinetic Thermal | $172.5k | 15 weeks | EMEA · ES | |
| FORGE Immersion Ready Interface Assembly 3 Part 4 approved alternate SKU | Apex Power Systems | $190.6k | 16 weeks | APAC · AU |
| FORGE Immersion Ready Interface Assembly 4 Part 1 approved primary SKU | Northstar Electrical | $134.3k | 17 weeks | NA · CA | |
| FORGE Immersion Ready Interface Assembly 4 Part 1 approved alternate SKU | HelioCool | $152.4k | 18 weeks | EMEA · DE | |
| FORGE Immersion Ready Interface Assembly 4 Part 1 approved alternate SKU | Vertex Modular | $170.5k | 19 weeks | APAC · AU | |
| FORGE Immersion Ready Interface Assembly 4 Part 1 approved alternate SKU | OmniControls | $188.6k | 20 weeks | NA · US |
| FORGE Immersion Ready Interface Assembly 4 Part 2 approved primary SKU | BlueRiver Fabrication | $142.3k | 21 weeks | EMEA · IE | |
| FORGE Immersion Ready Interface Assembly 4 Part 2 approved alternate SKU | Atlas Switchgear | $150.4k | 22 weeks | APAC · AU | |
| FORGE Immersion Ready Interface Assembly 4 Part 2 approved alternate SKU | Kinetic Thermal | $168.5k | 23 weeks | NA · CA | |
| FORGE Immersion Ready Interface Assembly 4 Part 2 approved alternate SKU | Apex Power Systems | $186.6k | 24 weeks | EMEA · GB |
| FORGE Immersion Ready Interface Assembly 4 Part 3 approved primary SKU | Northstar Electrical | $140.3k | 25 weeks | APAC · AU | |
| FORGE Immersion Ready Interface Assembly 4 Part 3 approved alternate SKU | HelioCool | $158.4k | 8 weeks | NA · US | |
| FORGE Immersion Ready Interface Assembly 4 Part 3 approved alternate SKU | Vertex Modular | $166.5k | 9 weeks | EMEA · NL | |
| FORGE Immersion Ready Interface Assembly 4 Part 3 approved alternate SKU | OmniControls | $184.6k | 10 weeks | APAC · AU |
| FORGE Immersion Ready Interface Assembly 4 Part 4 approved primary SKU | BlueRiver Fabrication | $138.3k | 11 weeks | NA · CA | |
| FORGE Immersion Ready Interface Assembly 4 Part 4 approved alternate SKU | Atlas Switchgear | $156.4k | 12 weeks | EMEA · AE | |
| FORGE Immersion Ready Interface Assembly 4 Part 4 approved alternate SKU | Kinetic Thermal | $174.5k | 13 weeks | APAC · AU | |
| FORGE Immersion Ready Interface Assembly 4 Part 4 approved alternate SKU | Apex Power Systems | $182.6k | 14 weeks | NA · US |
| FORGE Immersion Ready Interface Assembly 5 Part 1 approved primary SKU | Northstar Electrical | $136.3k | 15 weeks | EMEA · FR | |
| FORGE Immersion Ready Interface Assembly 5 Part 1 approved alternate SKU | HelioCool | $154.4k | 16 weeks | APAC · AU | |
| FORGE Immersion Ready Interface Assembly 5 Part 1 approved alternate SKU | Vertex Modular | $172.5k | 17 weeks | NA · CA | |
| FORGE Immersion Ready Interface Assembly 5 Part 1 approved alternate SKU | OmniControls | $190.6k | 18 weeks | EMEA · ES |
| FORGE Immersion Ready Interface Assembly 5 Part 2 approved primary SKU | BlueRiver Fabrication | $134.3k | 19 weeks | APAC · AU | |
| FORGE Immersion Ready Interface Assembly 5 Part 2 approved alternate SKU | Atlas Switchgear | $152.4k | 20 weeks | NA · US | |
| FORGE Immersion Ready Interface Assembly 5 Part 2 approved alternate SKU | Kinetic Thermal | $170.5k | 21 weeks | EMEA · DE | |
| FORGE Immersion Ready Interface Assembly 5 Part 2 approved alternate SKU | Apex Power Systems | $188.6k | 22 weeks | APAC · AU |
| FORGE Immersion Ready Interface Assembly 5 Part 3 approved primary SKU | Northstar Electrical | $142.3k | 23 weeks | NA · CA | |
| FORGE Immersion Ready Interface Assembly 5 Part 3 approved alternate SKU | HelioCool | $150.4k | 24 weeks | EMEA · IE | |
| FORGE Immersion Ready Interface Assembly 5 Part 3 approved alternate SKU | Vertex Modular | $168.5k | 25 weeks | APAC · AU | |
| FORGE Immersion Ready Interface Assembly 5 Part 3 approved alternate SKU | OmniControls | $186.6k | 8 weeks | NA · US |
| FORGE Immersion Ready Interface Assembly 5 Part 4 approved primary SKU | BlueRiver Fabrication | $140.3k | 9 weeks | EMEA · GB | |
| FORGE Immersion Ready Interface Assembly 5 Part 4 approved alternate SKU | Atlas Switchgear | $158.4k | 10 weeks | APAC · AU | |
| FORGE Immersion Ready Interface Assembly 5 Part 4 approved alternate SKU | Kinetic Thermal | $166.5k | 11 weeks | NA · CA | |
| FORGE Immersion Ready Interface Assembly 5 Part 4 approved alternate SKU | Apex Power Systems | $184.6k | 12 weeks | EMEA · NL |
| FORGE Liquid Distribution Assembly 1 Part 1 approved primary SKU | Northstar Electrical | $124.9k | 9 weeks | EMEA · NL | |
| FORGE Liquid Distribution Assembly 1 Part 1 approved alternate SKU | HelioCool | $141.3k | 10 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 1 Part 1 approved alternate SKU | Vertex Modular | $157.6k | 11 weeks | NA · CA | |
| FORGE Liquid Distribution Assembly 1 Part 1 approved alternate SKU | OmniControls | $164.9k | 12 weeks | EMEA · AE | |
| FORGE Liquid Distribution Assembly 1 Part 1 expedited cross-region alternate | Northstar Electrical | $44.8k | 18 weeks | EMEA · AE |
| FORGE Liquid Distribution Assembly 1 Part 2 approved primary SKU | BlueRiver Fabrication | $123.1k | 13 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 1 Part 2 approved alternate SKU | Atlas Switchgear | $139.4k | 14 weeks | NA · US | |
| FORGE Liquid Distribution Assembly 1 Part 2 approved alternate SKU | Kinetic Thermal | $155.8k | 15 weeks | EMEA · FR | |
| FORGE Liquid Distribution Assembly 1 Part 2 approved alternate SKU | Apex Power Systems | $172.2k | 16 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 1 Part 2 expedited cross-region alternate | HelioCool | $46k | 19 weeks | APAC · AU |
| FORGE Liquid Distribution Assembly 1 Part 3 approved primary SKU | Northstar Electrical | $121.3k | 17 weeks | NA · CA | |
| FORGE Liquid Distribution Assembly 1 Part 3 approved alternate SKU | HelioCool | $137.6k | 18 weeks | EMEA · ES | |
| FORGE Liquid Distribution Assembly 1 Part 3 approved alternate SKU | Vertex Modular | $154k | 19 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 1 Part 3 approved alternate SKU | OmniControls | $170.4k | 20 weeks | NA · US | |
| FORGE Liquid Distribution Assembly 1 Part 3 expedited cross-region alternate | Vertex Modular | $47.1k | 20 weeks | NA · CA |
| FORGE Liquid Distribution Assembly 1 Part 4 approved primary SKU | BlueRiver Fabrication | $128.5k | 21 weeks | EMEA · DE | |
| FORGE Liquid Distribution Assembly 1 Part 4 approved alternate SKU | Atlas Switchgear | $135.8k | 22 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 1 Part 4 approved alternate SKU | Kinetic Thermal | $152.2k | 23 weeks | NA · CA | |
| FORGE Liquid Distribution Assembly 1 Part 4 approved alternate SKU | Apex Power Systems | $168.5k | 24 weeks | EMEA · IE | |
| FORGE Liquid Distribution Assembly 1 Part 4 expedited cross-region alternate | OmniControls | $48.3k | 21 weeks | EMEA · FR |
| FORGE Liquid Distribution Assembly 2 Part 1 approved primary SKU | Northstar Electrical | $126.7k | 25 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 2 Part 1 approved alternate SKU | HelioCool | $143.1k | 8 weeks | NA · US | |
| FORGE Liquid Distribution Assembly 2 Part 1 approved alternate SKU | Vertex Modular | $150.4k | 9 weeks | EMEA · GB | |
| FORGE Liquid Distribution Assembly 2 Part 1 approved alternate SKU | OmniControls | $166.7k | 10 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 2 Part 1 expedited cross-region alternate | BlueRiver Fabrication | $49.4k | 22 weeks | APAC · AU |
| FORGE Liquid Distribution Assembly 2 Part 2 approved primary SKU | BlueRiver Fabrication | $124.9k | 11 weeks | NA · CA | |
| FORGE Liquid Distribution Assembly 2 Part 2 approved alternate SKU | Atlas Switchgear | $141.3k | 12 weeks | EMEA · NL | |
| FORGE Liquid Distribution Assembly 2 Part 2 approved alternate SKU | Kinetic Thermal | $157.6k | 13 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 2 Part 2 approved alternate SKU | Apex Power Systems | $164.9k | 14 weeks | NA · US | |
| FORGE Liquid Distribution Assembly 2 Part 2 expedited cross-region alternate | Atlas Switchgear | $50.6k | 23 weeks | NA · US |
| FORGE Liquid Distribution Assembly 2 Part 3 approved primary SKU | Northstar Electrical | $123.1k | 15 weeks | EMEA · AE | |
| FORGE Liquid Distribution Assembly 2 Part 3 approved alternate SKU | HelioCool | $139.4k | 16 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 2 Part 3 approved alternate SKU | Vertex Modular | $155.8k | 17 weeks | NA · CA | |
| FORGE Liquid Distribution Assembly 2 Part 3 approved alternate SKU | OmniControls | $172.2k | 18 weeks | EMEA · FR | |
| FORGE Liquid Distribution Assembly 2 Part 3 expedited cross-region alternate | Kinetic Thermal | $51.7k | 24 weeks | EMEA · ES |
| FORGE Liquid Distribution Assembly 2 Part 4 approved primary SKU | BlueRiver Fabrication | $121.3k | 19 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 2 Part 4 approved alternate SKU | Atlas Switchgear | $137.6k | 20 weeks | NA · US | |
| FORGE Liquid Distribution Assembly 2 Part 4 approved alternate SKU | Kinetic Thermal | $154k | 21 weeks | EMEA · ES | |
| FORGE Liquid Distribution Assembly 2 Part 4 approved alternate SKU | Apex Power Systems | $170.4k | 22 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 2 Part 4 expedited cross-region alternate | Apex Power Systems | $52.9k | 25 weeks | APAC · AU |
| FORGE Liquid Distribution Assembly 3 Part 1 approved primary SKU | Northstar Electrical | $128.5k | 23 weeks | NA · CA | |
| FORGE Liquid Distribution Assembly 3 Part 1 approved alternate SKU | HelioCool | $135.8k | 24 weeks | EMEA · DE | |
| FORGE Liquid Distribution Assembly 3 Part 1 approved alternate SKU | Vertex Modular | $152.2k | 25 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 3 Part 1 approved alternate SKU | OmniControls | $168.5k | 8 weeks | NA · US | |
| FORGE Liquid Distribution Assembly 3 Part 1 expedited cross-region alternate | Northstar Electrical | $54k | 26 weeks | NA · CA |
| FORGE Liquid Distribution Assembly 3 Part 2 approved primary SKU | BlueRiver Fabrication | $126.7k | 9 weeks | EMEA · IE | |
| FORGE Liquid Distribution Assembly 3 Part 2 approved alternate SKU | Atlas Switchgear | $143.1k | 10 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 3 Part 2 approved alternate SKU | Kinetic Thermal | $150.4k | 11 weeks | NA · CA | |
| FORGE Liquid Distribution Assembly 3 Part 2 approved alternate SKU | Apex Power Systems | $166.7k | 12 weeks | EMEA · GB | |
| FORGE Liquid Distribution Assembly 3 Part 2 expedited cross-region alternate | HelioCool | $55.2k | 27 weeks | EMEA · DE |
| FORGE Liquid Distribution Assembly 3 Part 3 approved primary SKU | Northstar Electrical | $124.9k | 13 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 3 Part 3 approved alternate SKU | HelioCool | $141.3k | 14 weeks | NA · US | |
| FORGE Liquid Distribution Assembly 3 Part 3 approved alternate SKU | Vertex Modular | $157.6k | 15 weeks | EMEA · NL | |
| FORGE Liquid Distribution Assembly 3 Part 3 approved alternate SKU | OmniControls | $164.9k | 16 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 3 Part 3 expedited cross-region alternate | Vertex Modular | $56.3k | 28 weeks | APAC · AU |
| FORGE Liquid Distribution Assembly 3 Part 4 approved primary SKU | BlueRiver Fabrication | $123.1k | 17 weeks | NA · CA | |
| FORGE Liquid Distribution Assembly 3 Part 4 approved alternate SKU | Atlas Switchgear | $139.4k | 18 weeks | EMEA · AE | |
| FORGE Liquid Distribution Assembly 3 Part 4 approved alternate SKU | Kinetic Thermal | $155.8k | 19 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 3 Part 4 approved alternate SKU | Apex Power Systems | $172.2k | 20 weeks | NA · US | |
| FORGE Liquid Distribution Assembly 3 Part 4 expedited cross-region alternate | OmniControls | $57.5k | 29 weeks | NA · US |
| FORGE Liquid Distribution Assembly 4 Part 1 approved primary SKU | Northstar Electrical | $121.3k | 21 weeks | EMEA · FR | |
| FORGE Liquid Distribution Assembly 4 Part 1 approved alternate SKU | HelioCool | $137.6k | 22 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 4 Part 1 approved alternate SKU | Vertex Modular | $154k | 23 weeks | NA · CA | |
| FORGE Liquid Distribution Assembly 4 Part 1 approved alternate SKU | OmniControls | $170.4k | 24 weeks | EMEA · ES | |
| FORGE Liquid Distribution Assembly 4 Part 1 expedited cross-region alternate | BlueRiver Fabrication | $58.6k | 30 weeks | EMEA · IE |
| FORGE Liquid Distribution Assembly 4 Part 2 approved primary SKU | BlueRiver Fabrication | $128.5k | 25 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 4 Part 2 approved alternate SKU | Atlas Switchgear | $135.8k | 8 weeks | NA · US | |
| FORGE Liquid Distribution Assembly 4 Part 2 approved alternate SKU | Kinetic Thermal | $152.2k | 9 weeks | EMEA · DE | |
| FORGE Liquid Distribution Assembly 4 Part 2 approved alternate SKU | Apex Power Systems | $168.5k | 10 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 4 Part 2 expedited cross-region alternate | Atlas Switchgear | $59.8k | 31 weeks | APAC · AU |
| FORGE Liquid Distribution Assembly 4 Part 3 approved primary SKU | Northstar Electrical | $126.7k | 11 weeks | NA · CA | |
| FORGE Liquid Distribution Assembly 4 Part 3 approved alternate SKU | HelioCool | $143.1k | 12 weeks | EMEA · IE | |
| FORGE Liquid Distribution Assembly 4 Part 3 approved alternate SKU | Vertex Modular | $150.4k | 13 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 4 Part 3 approved alternate SKU | OmniControls | $166.7k | 14 weeks | NA · US | |
| FORGE Liquid Distribution Assembly 4 Part 3 expedited cross-region alternate | Kinetic Thermal | $60.9k | 32 weeks | NA · CA |
| FORGE Liquid Distribution Assembly 4 Part 4 approved primary SKU | BlueRiver Fabrication | $124.9k | 15 weeks | EMEA · GB | |
| FORGE Liquid Distribution Assembly 4 Part 4 approved alternate SKU | Atlas Switchgear | $141.3k | 16 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 4 Part 4 approved alternate SKU | Kinetic Thermal | $157.6k | 17 weeks | NA · CA | |
| FORGE Liquid Distribution Assembly 4 Part 4 approved alternate SKU | Apex Power Systems | $164.9k | 18 weeks | EMEA · NL | |
| FORGE Liquid Distribution Assembly 4 Part 4 expedited cross-region alternate | Apex Power Systems | $62.1k | 33 weeks | EMEA · GB |
| FORGE Liquid Distribution Assembly 5 Part 1 approved primary SKU | Northstar Electrical | $123.1k | 19 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 5 Part 1 approved alternate SKU | HelioCool | $139.4k | 20 weeks | NA · US | |
| FORGE Liquid Distribution Assembly 5 Part 1 approved alternate SKU | Vertex Modular | $155.8k | 21 weeks | EMEA · AE | |
| FORGE Liquid Distribution Assembly 5 Part 1 approved alternate SKU | OmniControls | $172.2k | 22 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 5 Part 1 expedited cross-region alternate | Northstar Electrical | $63.2k | 34 weeks | APAC · AU |
| FORGE Liquid Distribution Assembly 5 Part 2 approved primary SKU | BlueRiver Fabrication | $121.3k | 23 weeks | NA · CA | |
| FORGE Liquid Distribution Assembly 5 Part 2 approved alternate SKU | Atlas Switchgear | $137.6k | 24 weeks | EMEA · FR | |
| FORGE Liquid Distribution Assembly 5 Part 2 approved alternate SKU | Kinetic Thermal | $154k | 25 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 5 Part 2 approved alternate SKU | Apex Power Systems | $170.4k | 8 weeks | NA · US | |
| FORGE Liquid Distribution Assembly 5 Part 2 expedited cross-region alternate | HelioCool | $64.4k | 35 weeks | NA · US |
| FORGE Liquid Distribution Assembly 5 Part 3 approved primary SKU | Northstar Electrical | $128.5k | 9 weeks | EMEA · ES | |
| FORGE Liquid Distribution Assembly 5 Part 3 approved alternate SKU | HelioCool | $135.8k | 10 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 5 Part 3 approved alternate SKU | Vertex Modular | $152.2k | 11 weeks | NA · CA | |
| FORGE Liquid Distribution Assembly 5 Part 3 approved alternate SKU | OmniControls | $168.5k | 12 weeks | EMEA · DE |
| FORGE Liquid Distribution Assembly 5 Part 4 approved primary SKU | BlueRiver Fabrication | $126.7k | 13 weeks | APAC · AU | |
| FORGE Liquid Distribution Assembly 5 Part 4 approved alternate SKU | Atlas Switchgear | $143.1k | 14 weeks | NA · US | |
| FORGE Liquid Distribution Assembly 5 Part 4 approved alternate SKU | Kinetic Thermal | $150.4k | 15 weeks | EMEA · IE | |
| FORGE Liquid Distribution Assembly 5 Part 4 approved alternate SKU | Apex Power Systems | $166.7k | 16 weeks | APAC · AU |
| Medium-Voltage Intake Assembly 1 Part 1 approved primary SKU | Northstar Electrical | $176.6k | 9 weeks | EMEA · DE | |
| Medium-Voltage Intake Assembly 1 Part 1 approved alternate SKU | HelioCool | $200.1k | 10 weeks | APAC · AU |
| Medium-Voltage Intake Assembly 1 Part 2 approved primary SKU | Vertex Modular | $181.8k | 11 weeks | NA · CA | |
| Medium-Voltage Intake Assembly 1 Part 2 approved alternate SKU | OmniControls | $205.3k | 12 weeks | EMEA · IE |
| Medium-Voltage Intake Assembly 1 Part 3 approved primary SKU | BlueRiver Fabrication | $174k | 13 weeks | APAC · AU | |
| Medium-Voltage Intake Assembly 1 Part 3 approved alternate SKU | Atlas Switchgear | $197.5k | 14 weeks | NA · US |
| Medium-Voltage Intake Assembly 1 Part 4 approved primary SKU | Kinetic Thermal | $179.2k | 15 weeks | EMEA · GB | |
| Medium-Voltage Intake Assembly 1 Part 4 approved alternate SKU | Apex Power Systems | $202.7k | 16 weeks | APAC · AU |
| Medium-Voltage Intake Assembly 1 Part 5 approved primary SKU | Northstar Electrical | $184.4k | 17 weeks | NA · CA | |
| Medium-Voltage Intake Assembly 1 Part 5 approved alternate SKU | HelioCool | $194.9k | 18 weeks | EMEA · NL |
| Medium-Voltage Intake Assembly 2 Part 1 approved primary SKU | Vertex Modular | $176.6k | 19 weeks | APAC · AU | |
| Medium-Voltage Intake Assembly 2 Part 1 approved alternate SKU | OmniControls | $200.1k | 20 weeks | NA · US |
| Medium-Voltage Intake Assembly 2 Part 2 approved primary SKU | BlueRiver Fabrication | $181.8k | 21 weeks | EMEA · AE | |
| Medium-Voltage Intake Assembly 2 Part 2 approved alternate SKU | Atlas Switchgear | $205.3k | 22 weeks | APAC · AU |
| Medium-Voltage Intake Assembly 2 Part 3 approved primary SKU | Kinetic Thermal | $174k | 23 weeks | NA · CA | |
| Medium-Voltage Intake Assembly 2 Part 3 approved alternate SKU | Apex Power Systems | $197.5k | 24 weeks | EMEA · FR |
| Medium-Voltage Intake Assembly 2 Part 4 approved primary SKU | Northstar Electrical | $179.2k | 25 weeks | APAC · AU | |
| Medium-Voltage Intake Assembly 2 Part 4 approved alternate SKU | HelioCool | $202.7k | 8 weeks | NA · US |
| Medium-Voltage Intake Assembly 2 Part 5 approved primary SKU | Vertex Modular | $184.4k | 9 weeks | EMEA · ES | |
| Medium-Voltage Intake Assembly 2 Part 5 approved alternate SKU | OmniControls | $194.9k | 10 weeks | APAC · AU |
| Medium-Voltage Intake Assembly 3 Part 1 approved primary SKU | BlueRiver Fabrication | $176.6k | 11 weeks | NA · CA | |
| Medium-Voltage Intake Assembly 3 Part 1 approved alternate SKU | Atlas Switchgear | $200.1k | 12 weeks | EMEA · DE |
| Medium-Voltage Intake Assembly 3 Part 2 approved primary SKU | Kinetic Thermal | $181.8k | 13 weeks | APAC · AU | |
| Medium-Voltage Intake Assembly 3 Part 2 approved alternate SKU | Apex Power Systems | $205.3k | 14 weeks | NA · US |
| Medium-Voltage Intake Assembly 3 Part 3 approved primary SKU | Northstar Electrical | $174k | 15 weeks | EMEA · IE | |
| Medium-Voltage Intake Assembly 3 Part 3 approved alternate SKU | HelioCool | $197.5k | 16 weeks | APAC · AU |
| Medium-Voltage Intake Assembly 3 Part 4 approved primary SKU | Vertex Modular | $179.2k | 17 weeks | NA · CA | |
| Medium-Voltage Intake Assembly 3 Part 4 approved alternate SKU | OmniControls | $202.7k | 18 weeks | EMEA · GB |
| Medium-Voltage Intake Assembly 3 Part 5 approved primary SKU | BlueRiver Fabrication | $184.4k | 19 weeks | APAC · AU | |
| Medium-Voltage Intake Assembly 3 Part 5 approved alternate SKU | Atlas Switchgear | $194.9k | 20 weeks | NA · US |
| Medium-Voltage Intake Assembly 4 Part 1 approved primary SKU | Kinetic Thermal | $176.6k | 21 weeks | EMEA · NL | |
| Medium-Voltage Intake Assembly 4 Part 1 approved alternate SKU | Apex Power Systems | $200.1k | 22 weeks | APAC · AU |
| Medium-Voltage Intake Assembly 4 Part 2 approved primary SKU | Northstar Electrical | $181.8k | 23 weeks | NA · CA | |
| Medium-Voltage Intake Assembly 4 Part 2 approved alternate SKU | HelioCool | $205.3k | 24 weeks | EMEA · AE |
| Medium-Voltage Intake Assembly 4 Part 3 approved primary SKU | Vertex Modular | $174k | 25 weeks | APAC · AU | |
| Medium-Voltage Intake Assembly 4 Part 3 approved alternate SKU | OmniControls | $197.5k | 8 weeks | NA · US |
| Medium-Voltage Intake Assembly 4 Part 4 approved primary SKU | BlueRiver Fabrication | $179.2k | 9 weeks | EMEA · FR | |
| Medium-Voltage Intake Assembly 4 Part 4 approved alternate SKU | Atlas Switchgear | $202.7k | 10 weeks | APAC · AU |
| Medium-Voltage Intake Assembly 4 Part 5 approved primary SKU | Kinetic Thermal | $184.4k | 11 weeks | NA · CA | |
| Medium-Voltage Intake Assembly 4 Part 5 approved alternate SKU | Apex Power Systems | $194.9k | 12 weeks | EMEA · ES |
| Medium-Voltage Intake Assembly 5 Part 1 approved primary SKU | Northstar Electrical | $176.6k | 13 weeks | APAC · AU | |
| Medium-Voltage Intake Assembly 5 Part 1 approved alternate SKU | HelioCool | $200.1k | 14 weeks | NA · US |
| Medium-Voltage Intake Assembly 5 Part 2 approved primary SKU | Vertex Modular | $181.8k | 15 weeks | EMEA · DE | |
| Medium-Voltage Intake Assembly 5 Part 2 approved alternate SKU | OmniControls | $205.3k | 16 weeks | APAC · AU |
| Medium-Voltage Intake Assembly 5 Part 3 approved primary SKU | BlueRiver Fabrication | $174k | 17 weeks | NA · CA | |
| Medium-Voltage Intake Assembly 5 Part 3 approved alternate SKU | Atlas Switchgear | $197.5k | 18 weeks | EMEA · IE |
| Medium-Voltage Intake Assembly 5 Part 4 approved primary SKU | Kinetic Thermal | $179.2k | 19 weeks | APAC · AU | |
| Medium-Voltage Intake Assembly 5 Part 4 approved alternate SKU | Apex Power Systems | $202.7k | 20 weeks | NA · US |
| Medium-Voltage Intake Assembly 5 Part 5 approved primary SKU | Northstar Electrical | $184.4k | 21 weeks | EMEA · GB | |
| Medium-Voltage Intake Assembly 5 Part 5 approved alternate SKU | HelioCool | $194.9k | 22 weeks | APAC · AU |
| Power Distribution Assembly 1 Part 1 approved primary SKU | BlueRiver Fabrication | $220.5k | 21 weeks | EMEA · GB | |
| Power Distribution Assembly 1 Part 1 approved alternate SKU | Atlas Switchgear | $249.8k | 22 weeks | APAC · AU |
| Power Distribution Assembly 1 Part 2 approved primary SKU | Kinetic Thermal | $227k | 23 weeks | NA · CA | |
| Power Distribution Assembly 1 Part 2 approved alternate SKU | Apex Power Systems | $256.3k | 24 weeks | EMEA · NL |
| Power Distribution Assembly 1 Part 3 approved primary SKU | Northstar Electrical | $217.2k | 25 weeks | APAC · AU | |
| Power Distribution Assembly 1 Part 3 approved alternate SKU | HelioCool | $246.5k | 8 weeks | NA · US |
| Power Distribution Assembly 1 Part 4 approved primary SKU | Vertex Modular | $223.7k | 9 weeks | EMEA · AE | |
| Power Distribution Assembly 1 Part 4 approved alternate SKU | OmniControls | $253k | 10 weeks | APAC · AU |
| Power Distribution Assembly 1 Part 5 approved primary SKU | BlueRiver Fabrication | $230.2k | 11 weeks | NA · CA | |
| Power Distribution Assembly 1 Part 5 approved alternate SKU | Atlas Switchgear | $243.3k | 12 weeks | EMEA · FR |
| Power Distribution Assembly 2 Part 1 approved primary SKU | Kinetic Thermal | $220.5k | 13 weeks | APAC · AU | |
| Power Distribution Assembly 2 Part 1 approved alternate SKU | Apex Power Systems | $249.8k | 14 weeks | NA · US |
| Power Distribution Assembly 2 Part 2 approved primary SKU | Northstar Electrical | $227k | 15 weeks | EMEA · ES | |
| Power Distribution Assembly 2 Part 2 approved alternate SKU | HelioCool | $256.3k | 16 weeks | APAC · AU |
| Power Distribution Assembly 2 Part 3 approved primary SKU | Vertex Modular | $217.2k | 17 weeks | NA · CA | |
| Power Distribution Assembly 2 Part 3 approved alternate SKU | OmniControls | $246.5k | 18 weeks | EMEA · DE |
| Power Distribution Assembly 2 Part 4 approved primary SKU | BlueRiver Fabrication | $223.7k | 19 weeks | APAC · AU | |
| Power Distribution Assembly 2 Part 4 approved alternate SKU | Atlas Switchgear | $253k | 20 weeks | NA · US |
| Power Distribution Assembly 2 Part 5 approved primary SKU | Kinetic Thermal | $230.2k | 21 weeks | EMEA · IE | |
| Power Distribution Assembly 2 Part 5 approved alternate SKU | Apex Power Systems | $243.3k | 22 weeks | APAC · AU |
| Power Distribution Assembly 3 Part 1 approved primary SKU | Northstar Electrical | $220.5k | 23 weeks | NA · CA | |
| Power Distribution Assembly 3 Part 1 approved alternate SKU | HelioCool | $249.8k | 24 weeks | EMEA · GB |
| Power Distribution Assembly 3 Part 2 approved primary SKU | Vertex Modular | $227k | 25 weeks | APAC · AU | |
| Power Distribution Assembly 3 Part 2 approved alternate SKU | OmniControls | $256.3k | 8 weeks | NA · US |
| Power Distribution Assembly 3 Part 3 approved primary SKU | BlueRiver Fabrication | $217.2k | 9 weeks | EMEA · NL | |
| Power Distribution Assembly 3 Part 3 approved alternate SKU | Atlas Switchgear | $246.5k | 10 weeks | APAC · AU |
| Power Distribution Assembly 3 Part 4 approved primary SKU | Kinetic Thermal | $223.7k | 11 weeks | NA · CA | |
| Power Distribution Assembly 3 Part 4 approved alternate SKU | Apex Power Systems | $253k | 12 weeks | EMEA · AE |
| Power Distribution Assembly 3 Part 5 approved primary SKU | Northstar Electrical | $230.2k | 13 weeks | APAC · AU | |
| Power Distribution Assembly 3 Part 5 approved alternate SKU | HelioCool | $243.3k | 14 weeks | NA · US |
| Power Distribution Assembly 4 Part 1 approved primary SKU | Vertex Modular | $220.5k | 15 weeks | EMEA · FR | |
| Power Distribution Assembly 4 Part 1 approved alternate SKU | OmniControls | $249.8k | 16 weeks | APAC · AU |
| Power Distribution Assembly 4 Part 2 approved primary SKU | BlueRiver Fabrication | $227k | 17 weeks | NA · CA | |
| Power Distribution Assembly 4 Part 2 approved alternate SKU | Atlas Switchgear | $256.3k | 18 weeks | EMEA · ES |
| Power Distribution Assembly 4 Part 3 approved primary SKU | Kinetic Thermal | $217.2k | 19 weeks | APAC · AU | |
| Power Distribution Assembly 4 Part 3 approved alternate SKU | Apex Power Systems | $246.5k | 20 weeks | NA · US |
| Power Distribution Assembly 4 Part 4 approved primary SKU | Northstar Electrical | $223.7k | 21 weeks | EMEA · DE | |
| Power Distribution Assembly 4 Part 4 approved alternate SKU | HelioCool | $253k | 22 weeks | APAC · AU |
| Power Distribution Assembly 4 Part 5 approved primary SKU | Vertex Modular | $230.2k | 23 weeks | NA · CA | |
| Power Distribution Assembly 4 Part 5 approved alternate SKU | OmniControls | $243.3k | 24 weeks | EMEA · IE |
| Power Distribution Assembly 5 Part 1 approved primary SKU | BlueRiver Fabrication | $220.5k | 25 weeks | APAC · AU | |
| Power Distribution Assembly 5 Part 1 approved alternate SKU | Atlas Switchgear | $249.8k | 8 weeks | NA · US |
| Power Distribution Assembly 5 Part 2 approved primary SKU | Kinetic Thermal | $227k | 9 weeks | EMEA · GB | |
| Power Distribution Assembly 5 Part 2 approved alternate SKU | Apex Power Systems | $256.3k | 10 weeks | APAC · AU |
| Power Distribution Assembly 5 Part 3 approved primary SKU | Northstar Electrical | $217.2k | 11 weeks | NA · CA | |
| Power Distribution Assembly 5 Part 3 approved alternate SKU | HelioCool | $246.5k | 12 weeks | EMEA · NL |
| Power Distribution Assembly 5 Part 4 approved primary SKU | Vertex Modular | $223.7k | 13 weeks | APAC · AU | |
| Power Distribution Assembly 5 Part 4 approved alternate SKU | OmniControls | $253k | 14 weeks | NA · US |
| Power Distribution Assembly 5 Part 5 approved primary SKU | BlueRiver Fabrication | $230.2k | 15 weeks | EMEA · AE | |
| Power Distribution Assembly 5 Part 5 approved alternate SKU | Atlas Switchgear | $243.3k | 16 weeks | APAC · AU |
| Security and Network Assembly 1 Part 1 approved primary SKU | Kinetic Thermal | $198.5k | 15 weeks | EMEA · IE | |
| Security and Network Assembly 1 Part 1 approved alternate SKU | Apex Power Systems | $224.9k | 16 weeks | APAC · AU |
| Security and Network Assembly 1 Part 2 approved primary SKU | Northstar Electrical | $204.4k | 17 weeks | NA · CA | |
| Security and Network Assembly 1 Part 2 approved alternate SKU | HelioCool | $230.8k | 18 weeks | EMEA · GB |
| Security and Network Assembly 1 Part 3 approved primary SKU | Vertex Modular | $195.6k | 19 weeks | APAC · AU | |
| Security and Network Assembly 1 Part 3 approved alternate SKU | OmniControls | $222k | 20 weeks | NA · US |
| Security and Network Assembly 1 Part 4 approved primary SKU | BlueRiver Fabrication | $201.5k | 21 weeks | EMEA · NL | |
| Security and Network Assembly 1 Part 4 approved alternate SKU | Atlas Switchgear | $227.9k | 22 weeks | APAC · AU |
| Security and Network Assembly 1 Part 5 approved primary SKU | Kinetic Thermal | $207.3k | 23 weeks | NA · CA | |
| Security and Network Assembly 1 Part 5 approved alternate SKU | Apex Power Systems | $219.1k | 24 weeks | EMEA · AE |
| Security and Network Assembly 2 Part 1 approved primary SKU | Northstar Electrical | $198.5k | 25 weeks | APAC · AU | |
| Security and Network Assembly 2 Part 1 approved alternate SKU | HelioCool | $224.9k | 8 weeks | NA · US |
| Security and Network Assembly 2 Part 2 approved primary SKU | Vertex Modular | $204.4k | 9 weeks | EMEA · FR | |
| Security and Network Assembly 2 Part 2 approved alternate SKU | OmniControls | $230.8k | 10 weeks | APAC · AU |
| Security and Network Assembly 2 Part 3 approved primary SKU | BlueRiver Fabrication | $195.6k | 11 weeks | NA · CA | |
| Security and Network Assembly 2 Part 3 approved alternate SKU | Atlas Switchgear | $222k | 12 weeks | EMEA · ES |
| Security and Network Assembly 2 Part 4 approved primary SKU | Kinetic Thermal | $201.5k | 13 weeks | APAC · AU | |
| Security and Network Assembly 2 Part 4 approved alternate SKU | Apex Power Systems | $227.9k | 14 weeks | NA · US |
| Security and Network Assembly 2 Part 5 approved primary SKU | Northstar Electrical | $207.3k | 15 weeks | EMEA · DE | |
| Security and Network Assembly 2 Part 5 approved alternate SKU | HelioCool | $219.1k | 16 weeks | APAC · AU |
| Security and Network Assembly 3 Part 1 approved primary SKU | Vertex Modular | $198.5k | 17 weeks | NA · CA | |
| Security and Network Assembly 3 Part 1 approved alternate SKU | OmniControls | $224.9k | 18 weeks | EMEA · IE |
| Security and Network Assembly 3 Part 2 approved primary SKU | BlueRiver Fabrication | $204.4k | 19 weeks | APAC · AU | |
| Security and Network Assembly 3 Part 2 approved alternate SKU | Atlas Switchgear | $230.8k | 20 weeks | NA · US |
| Security and Network Assembly 3 Part 3 approved primary SKU | Kinetic Thermal | $195.6k | 21 weeks | EMEA · GB | |
| Security and Network Assembly 3 Part 3 approved alternate SKU | Apex Power Systems | $222k | 22 weeks | APAC · AU |
| Security and Network Assembly 3 Part 4 approved primary SKU | Northstar Electrical | $201.5k | 23 weeks | NA · CA | |
| Security and Network Assembly 3 Part 4 approved alternate SKU | HelioCool | $227.9k | 24 weeks | EMEA · NL |
| Security and Network Assembly 3 Part 5 approved primary SKU | Vertex Modular | $207.3k | 25 weeks | APAC · AU | |
| Security and Network Assembly 3 Part 5 approved alternate SKU | OmniControls | $219.1k | 8 weeks | NA · US |
| Security and Network Assembly 4 Part 1 approved primary SKU | BlueRiver Fabrication | $198.5k | 9 weeks | EMEA · AE | |
| Security and Network Assembly 4 Part 1 approved alternate SKU | Atlas Switchgear | $224.9k | 10 weeks | APAC · AU |
| Security and Network Assembly 4 Part 2 approved primary SKU | Kinetic Thermal | $204.4k | 11 weeks | NA · CA | |
| Security and Network Assembly 4 Part 2 approved alternate SKU | Apex Power Systems | $230.8k | 12 weeks | EMEA · FR |
| Security and Network Assembly 4 Part 3 approved primary SKU | Northstar Electrical | $195.6k | 13 weeks | APAC · AU | |
| Security and Network Assembly 4 Part 3 approved alternate SKU | HelioCool | $222k | 14 weeks | NA · US |
| Security and Network Assembly 4 Part 4 approved primary SKU | Vertex Modular | $201.5k | 15 weeks | EMEA · ES | |
| Security and Network Assembly 4 Part 4 approved alternate SKU | OmniControls | $227.9k | 16 weeks | APAC · AU |
| Security and Network Assembly 4 Part 5 approved primary SKU | BlueRiver Fabrication | $207.3k | 17 weeks | NA · CA | |
| Security and Network Assembly 4 Part 5 approved alternate SKU | Atlas Switchgear | $219.1k | 18 weeks | EMEA · DE |
| Security and Network Assembly 5 Part 1 approved primary SKU | Kinetic Thermal | $198.5k | 19 weeks | APAC · AU | |
| Security and Network Assembly 5 Part 1 approved alternate SKU | Apex Power Systems | $224.9k | 20 weeks | NA · US |
| Security and Network Assembly 5 Part 2 approved primary SKU | Northstar Electrical | $204.4k | 21 weeks | EMEA · IE | |
| Security and Network Assembly 5 Part 2 approved alternate SKU | HelioCool | $230.8k | 22 weeks | APAC · AU |
| Security and Network Assembly 5 Part 3 approved primary SKU | Vertex Modular | $195.6k | 23 weeks | NA · CA | |
| Security and Network Assembly 5 Part 3 approved alternate SKU | OmniControls | $222k | 24 weeks | EMEA · GB |
| Security and Network Assembly 5 Part 4 approved primary SKU | BlueRiver Fabrication | $201.5k | 25 weeks | APAC · AU | |
| Security and Network Assembly 5 Part 4 approved alternate SKU | Atlas Switchgear | $227.9k | 8 weeks | NA · US |
| Security and Network Assembly 5 Part 5 approved primary SKU | Kinetic Thermal | $207.3k | 9 weeks | EMEA · NL | |
| Security and Network Assembly 5 Part 5 approved alternate SKU | Apex Power Systems | $219.1k | 10 weeks | APAC · AU |
| Structural Kit Assembly 1 Part 1 approved primary SKU | Vertex Modular | $213.2k | 25 weeks | APAC · AU | |
| Structural Kit Assembly 1 Part 1 approved alternate SKU | OmniControls | $241.5k | 8 weeks | NA · US |
| Structural Kit Assembly 1 Part 2 approved primary SKU | BlueRiver Fabrication | $219.5k | 9 weeks | EMEA · DE | |
| Structural Kit Assembly 1 Part 2 approved alternate SKU | Atlas Switchgear | $247.8k | 10 weeks | APAC · AU |
| Structural Kit Assembly 1 Part 3 approved primary SKU | Kinetic Thermal | $210k | 11 weeks | NA · CA | |
| Structural Kit Assembly 1 Part 3 approved alternate SKU | Apex Power Systems | $238.4k | 12 weeks | EMEA · IE |
| Structural Kit Assembly 1 Part 4 approved primary SKU | Northstar Electrical | $216.3k | 13 weeks | APAC · AU | |
| Structural Kit Assembly 1 Part 4 approved alternate SKU | HelioCool | $244.7k | 14 weeks | NA · US |
| Structural Kit Assembly 1 Part 5 approved primary SKU | Vertex Modular | $222.6k | 15 weeks | EMEA · GB | |
| Structural Kit Assembly 1 Part 5 approved alternate SKU | OmniControls | $235.2k | 16 weeks | APAC · AU |
| Structural Kit Assembly 2 Part 1 approved primary SKU | BlueRiver Fabrication | $213.2k | 17 weeks | NA · CA | |
| Structural Kit Assembly 2 Part 1 approved alternate SKU | Atlas Switchgear | $241.5k | 18 weeks | EMEA · NL |
| Structural Kit Assembly 2 Part 2 approved primary SKU | Kinetic Thermal | $219.5k | 19 weeks | APAC · AU | |
| Structural Kit Assembly 2 Part 2 approved alternate SKU | Apex Power Systems | $247.8k | 20 weeks | NA · US |
| Structural Kit Assembly 2 Part 3 approved primary SKU | Northstar Electrical | $210k | 21 weeks | EMEA · AE | |
| Structural Kit Assembly 2 Part 3 approved alternate SKU | HelioCool | $238.4k | 22 weeks | APAC · AU |
| Structural Kit Assembly 2 Part 4 approved primary SKU | Vertex Modular | $216.3k | 23 weeks | NA · CA | |
| Structural Kit Assembly 2 Part 4 approved alternate SKU | OmniControls | $244.7k | 24 weeks | EMEA · FR |
| Structural Kit Assembly 2 Part 5 approved primary SKU | BlueRiver Fabrication | $222.6k | 25 weeks | APAC · AU | |
| Structural Kit Assembly 2 Part 5 approved alternate SKU | Atlas Switchgear | $235.2k | 8 weeks | NA · US |
| Structural Kit Assembly 3 Part 1 approved primary SKU | Kinetic Thermal | $213.2k | 9 weeks | EMEA · ES | |
| Structural Kit Assembly 3 Part 1 approved alternate SKU | Apex Power Systems | $241.5k | 10 weeks | APAC · AU |
| Structural Kit Assembly 3 Part 2 approved primary SKU | Northstar Electrical | $219.5k | 11 weeks | NA · CA | |
| Structural Kit Assembly 3 Part 2 approved alternate SKU | HelioCool | $247.8k | 12 weeks | EMEA · DE |
| Structural Kit Assembly 3 Part 3 approved primary SKU | Vertex Modular | $210k | 13 weeks | APAC · AU | |
| Structural Kit Assembly 3 Part 3 approved alternate SKU | OmniControls | $238.4k | 14 weeks | NA · US |
| Structural Kit Assembly 3 Part 4 approved primary SKU | BlueRiver Fabrication | $216.3k | 15 weeks | EMEA · IE | |
| Structural Kit Assembly 3 Part 4 approved alternate SKU | Atlas Switchgear | $244.7k | 16 weeks | APAC · AU |
| Structural Kit Assembly 3 Part 5 approved primary SKU | Kinetic Thermal | $222.6k | 17 weeks | NA · CA | |
| Structural Kit Assembly 3 Part 5 approved alternate SKU | Apex Power Systems | $235.2k | 18 weeks | EMEA · GB |
| Structural Kit Assembly 4 Part 1 approved primary SKU | Northstar Electrical | $213.2k | 19 weeks | APAC · AU | |
| Structural Kit Assembly 4 Part 1 approved alternate SKU | HelioCool | $241.5k | 20 weeks | NA · US |
| Structural Kit Assembly 4 Part 2 approved primary SKU | Vertex Modular | $219.5k | 21 weeks | EMEA · NL | |
| Structural Kit Assembly 4 Part 2 approved alternate SKU | OmniControls | $247.8k | 22 weeks | APAC · AU |
| Structural Kit Assembly 4 Part 3 approved primary SKU | BlueRiver Fabrication | $210k | 23 weeks | NA · CA | |
| Structural Kit Assembly 4 Part 3 approved alternate SKU | Atlas Switchgear | $238.4k | 24 weeks | EMEA · AE |
| Structural Kit Assembly 4 Part 4 approved primary SKU | Kinetic Thermal | $216.3k | 25 weeks | APAC · AU | |
| Structural Kit Assembly 4 Part 4 approved alternate SKU | Apex Power Systems | $244.7k | 8 weeks | NA · US |
| Structural Kit Assembly 4 Part 5 approved primary SKU | Northstar Electrical | $222.6k | 9 weeks | EMEA · FR | |
| Structural Kit Assembly 4 Part 5 approved alternate SKU | HelioCool | $235.2k | 10 weeks | APAC · AU |
| Structural Kit Assembly 5 Part 1 approved primary SKU | Vertex Modular | $213.2k | 11 weeks | NA · CA | |
| Structural Kit Assembly 5 Part 1 approved alternate SKU | OmniControls | $241.5k | 12 weeks | EMEA · ES |
| Structural Kit Assembly 5 Part 2 approved primary SKU | BlueRiver Fabrication | $219.5k | 13 weeks | APAC · AU | |
| Structural Kit Assembly 5 Part 2 approved alternate SKU | Atlas Switchgear | $247.8k | 14 weeks | NA · US |
| Structural Kit Assembly 5 Part 3 approved primary SKU | Kinetic Thermal | $210k | 15 weeks | EMEA · DE | |
| Structural Kit Assembly 5 Part 3 approved alternate SKU | Apex Power Systems | $238.4k | 16 weeks | APAC · AU |
| Structural Kit Assembly 5 Part 4 approved primary SKU | Northstar Electrical | $216.3k | 17 weeks | NA · CA | |
| Structural Kit Assembly 5 Part 4 approved alternate SKU | HelioCool | $244.7k | 18 weeks | EMEA · IE |
| Structural Kit Assembly 5 Part 5 approved primary SKU | Vertex Modular | $222.6k | 19 weeks | APAC · AU | |
| Structural Kit Assembly 5 Part 5 approved alternate SKU | OmniControls | $235.2k | 20 weeks | NA · US |